GRACE i CONTRACTING CORP.
151-46 6th Roa[J, Whitestone, N.Y. 11357-(71B) 767-9000
DATE: DECEMBER 7, 2001 (DAY FINAL)
1_____________
DAILY WORK FORCE REPORT
Job Name & Location: World Trade Center
Contract No.
Weather Ccjnditions
Labor Equipment
CLASSIFICATION QUANT. Description MANNED STANDBY IDLE
SUPERINTENDENT , 2 CAT 966 LOADER 1
PROJECT Engineer , 2 CAT 446 BACKHOE 1
OFFICE ENGINEER CAT 973 LOADER 1
FOREMEN i ; CAT 365 GRAPPLER 1
SAFETY OFFICER ; 1 CAT 375 GRAPPLER 1
LABORERS' 19 HITACHI 750 GRAPPLER 1
IRON WORKERS 1 HITACHI 550 GRAPPLER 1
LOCAL 14 j 4 HITACHI 550 GRAPPLER 1
LOCAL 15 8 HITACHI 1200 GRAPPLER 1
CARPENTER 1 185 CFM COMPRESSOFI 1
CARPENTER FOREMAN 1 235 HAMMER HOE RAM 1
TEAMSTERS 10 MECHANICS TRUCK 2
MECHANIC^ 2 TOOL TRUCK 1
HOUSE WF^ECKERS ; 6 TOOL VAN 1
ROLL OFF___________ ■
DUMP TRAILERS 7
LOW BED TRAILER '
'ELIVERIEg: AWISCO ,_______ HIGH DECK TRAILERS ' 2
' AUSTER RUBBER WELDING TRUCK 1
FUEL TRUCK 1
PICKUP TRUCKS 8
LIGHT TOWERS 13
SITE MULE 3
DUMP TRUCKS
10 WHEEL DUMP TRUC(<
FLASHING ARROW BOARD 1
OFFICE TRAILER/GENe'^ 1
CARGO BOXES j 3 L
FLAT TRUCK ' i1
PUMP 2
ROLLER ;1
RAINMAKER/GENIE LIFT 1
Description Work:
LOADS OUT: 60 YUKE LOADS 30_____________ I
LOAD OUT STEEL AND DEBRIS
MANNED TARPING AND TRIMMING STATIONS 4-
MANNED Water stations for dust control I
MAINTAIN Traffic flow in and out of area
CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF NW CORNER OF TOWER 2 T;O MEET AMEC'S ROADWAY
CONTINUEIBURNING OF THE SW CORNER COLUMN BEAMS !
ELEVATIONS: ALL MACHINES LEVEL B-5 253
GRAQE CONTRACTING.CORP)
Approved By:
Title: ' :
^■fot: SUPERINTENDENT
DAILY WORK FORCE REPORT 1207D.xls