Grace Contracting daily workforce report, WTC

Machine-extracted title · confidence 40%

Daily workforce and equipment log for WTC site operations.

NYC-WTC_000278845
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

GRACE CONTRACTING CORP. i5i.*»smRoao. wbkMian*, N.v, na67. (7i8)7e7.8uoo DATE: 2/3/02 NIOHT FINAL

DAILY WORK FORCE REPORT

Job Name & Location: World Trade Center Contract No. Weather Conditions:

Lahor 1 Equipment classification □UANT. 1 DeecripBon MANNED iSTANDBy TOLEj SUPERINTENDENT CAT 966 LOADER 1 I PROJECT ENGINEER 1 CAT 365 GRAPPLER 1 OFFICE ENGINEER CAT 375 GRAPPLER 1 1 FOREMEN 2 HITACHI 750 GRAPPLER 1 SAFETY OFFICER HITACH11200 GRAPPLER 1 LABORERS 12 185 CFM COMPRESSOR SEE NOTE’ IRON WORKERS Z3S HAMMER HOE RAM 1 LOCAL 14 4 MECHANICS TRUCK 1 1 LOCAL 15 s' TOOL TRUCK CARPENTER TOOL VAN CARPENTER FOREMAN ROLL OFF TEAMSTERS [FUEL. TRAILER DELIVERY) 1 DUMP TRAILERS 8 TEAMSTERS (fLaTBEDS, DUMPS, AND FUKES) 14 buKES' ______ a MECHANICS 1 HIGH DECK TRAILERS 2' HOUSE WRECKERS jWELDING TRUCK ~ BFUELTRUCK 1 ilPICKUP TRUCKS ' 3' Light TOWERS 6 DELIVERIES:_____________________________ SITE MULE 3 -COMPRESSOR RAN DURING SHIFT UNMANNED* DUMP TRUCKS 10 WHEEL DUMP TRUCK flashing ARROW BOARD OFFICE TRAILER/GENER. 1 CARGO BOXES 4 FLAT TRUCK 1 PUMP

D&senptiqn ot Work’ COMPLETED WORK_______ ________ ________ _______________________ CONTINUED to REMOVE DEBRIS FROM LOWER LEVELS OF WO COMPLEX. MACHINES AT EL. 86 maintained TRAFFIC FLOW INTO AND OUT OF AREA~~ RECORDED TIMES ANC NUMBERS OF TRUCK LOADS OF DEBRIS FROM SITE LOADS OUT: 101_______ ___________ __________ YUKES: 168 DDT LOADS: 93 __ ___________________________ ______________________________________________ DELAYS: RECOVERY IN TOWER 1 SLOWED PRODUCTION DURING FIRST 3 HOURS; 1200 LOST IHR 02O0-Q30D

GRACE CONTRACTING CORP Approved By: BY: Title; T EUPEHIhrreNOENT For:

daily work force HHPORT02C3N.xls

CITY_21MC100_004633758

NYC-WTC_000278845

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000278845Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →