GRACE CONTRACTING CORP.
ft 51-45 Sth Road, Whitestone, N.Y. 11357- (718) 767-9000 i DATE:
DAILY WORK FORCE REPORT DECEMBER 5. 2001 (NIGHT FINAL)
________________ ______________ Job Name & Lo cation; World Trade Center Contract No. Weather Conditions
Labor |[|_ Equipment CLASSIFICATION QUANT, iIr Description MANNED STANDBY idle! 2 [bcat 966 LOADER SUPERINTENDENT ; PROJECT ENGINEER 1 hCAT 446 BACKHOE OFFICE ENGINEER_______________ _____ 1 CAT 973 LOADER 1 FOREMEN 2 CAT 365 GRAPPLER 1 SAFETY OFFIC:ER CAT 375 GRAPPLER 6 Hrs. 6 Hrs, i LABORERS 20 HITACHI 750 GRAPPLER 1 [hITACHI 550 GRAPPLER IRON WORKERS ' 1 LOCAL 14___________________ 5 HITACHI 550 GRAPPLER ~ 1 LOCAL 15 8 HITACHI 1200 GRAPPLER~ 1 ||l85 CFM COMPRESSOR 1 CARPENTER CARPENTER FOREMAN 235 HAMMER HOE RAM 6 Hrs. 6 Hrs. TEAMSTERS 10 MECHANICS TRUCK 1 1 MECHANICS 1 TOOLTRUCK 1 i HOUSE WRECKERS 10 TOOLVAN ROLL OFF DUMP TRAILERS 7 LOW BED TRAILER HIGH DECK TRAILERS 2 WELDING TRUCK FUEL TRUCK 1 PICKUP TRUCKS 2 LIGHT TOWERS 13 SITE MULE 3 DUMP TRUCKS 10 WHEEL DUMP TRUCK FLASHING ARROW BOARD 1 OFFICE TRAILER/GENER. 1 CARGO BOXES 3 ■ FLAT TRUCK 1 ' PUMP 2 ■ ROLLER 1 ■ RAINMAKER/GENIE LIFT 1
Description of Work: _________________________________________________________________________________ LOADS OUT; 27 HI-BEDS/DUMP TRAILERS; 34 EUCLIDS LOAD OUT STEEL AND DEBRIS_____________________________________________________________________ j MAN TARPING AND TRIMMING STATIONS____________________________________________________ __________ ; MAN WATER STATIONS FOR DUST CONTROL ; CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF NW CORNER OF TOWER 2 TO MEET AMEC'S ROADWAY ELEVATIONS: ALL MACHINES LEVEL B-5 253 j DELAYS FROM 7-10PM FOR FREON RECOVERY; AND MULTIPLE BODY RECOVERIES THROUGHOUT THE NIGHT GRACE CONTRACTING CORP Approved By; Title: For: SUPERINTENDENT (J'
DAILY WORK FORCE REPORT 1205N.xls
CITY_21MC100_004688225
NYC-WTC_000278619
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000429737
Asbestos fiber analysis result from WTC area NW of Bankr, Jan 2002.
3 shared non-person entities · 1 shared topics · similarity 0.993
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000361548
Night final daily workforce and equipment for World Trade Center site, Dec 5, 2001.
3 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000408093
Daily workforce and equipment details for World Trade Center site, December 12, 2001 (Day).
2 shared non-person entities · 1 shared topics · similarity 0.987
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305052
Daily workforce and equipment record for World Trade Center site, December 2001.
2 shared non-person entities · 1 shared topics · similarity 0.985
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000278686
Night shift workforce and equipment counts for World Trade Center, December 5, 2001.
3 shared non-person entities · 1 shared topics · similarity 0.985
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429740
Daily labor and equipment classifications for World Trade Center project, Dec 2001.
2 shared non-person entities · 1 shared topics · similarity 0.985
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305381
Night final daily workforce report with weather, World Trade Center, Dec 8, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.985
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000278997
Daytime daily workforce and equipment at World Trade site, December 6, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.985
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305051
Night final daily workforce and equipment roster for World Trade Center project, December 2001.
1 shared non-person entities · 1 shared topics · similarity 0.984
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000408086
Night shift daily workforce and equipment roster for World Trade site, Dec 15, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.984
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305609
Day final daily workforce and equipment at World Trade Center site, December 2001.
2 shared non-person entities · 1 shared topics · similarity 0.984
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000266918
Night final daily workforce summary for World Trade Center project.
3 shared non-person entities · 1 shared topics · similarity 0.983
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000429737
Asbestos fiber analysis result from WTC area NW of Bankr, Jan 2002.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000361548
Night final daily workforce and equipment for World Trade Center site, Dec 5, 2001.
Similarity score 0.995 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000408093
Daily workforce and equipment details for World Trade Center site, December 12, 2001 (Day).
Similarity score 0.994 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305052
Daily workforce and equipment record for World Trade Center site, December 2001.
Similarity score 0.993 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000278686
Night shift workforce and equipment counts for World Trade Center, December 5, 2001.
Similarity score 0.992 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429740
Daily labor and equipment classifications for World Trade Center project, Dec 2001.
Similarity score 0.992 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000429737
Asbestos fiber analysis result from WTC area NW of Bankr, Jan 2002.
Similar indexed content
NYC-WTC_000361548
Night final daily workforce and equipment for World Trade Center site, Dec 5, 2001.
Similar indexed content
NYC-WTC_000408093
Daily workforce and equipment details for World Trade Center site, December 12, 2001 (Day).
Similar indexed content
NYC-WTC_000305052
Daily workforce and equipment record for World Trade Center site, December 2001.
Similar indexed content
NYC-WTC_000278686
Night shift workforce and equipment counts for World Trade Center, December 5, 2001.
Similar indexed content