(i) Limitation. If it is found during Phase HB, that the non-friable ACM or asbestos material will become friable during the removal process, abatement work must stop immediately while the remote personal decontamination system is relocated to be attached and contiguous to the regulated abatement work area. The following requirements apply for all remote personal decontamination systems: (1) Protective Clothing. Workers shall don two (2) sets of disposable protective clothing and a supply of protective clothing shall be kept in the airlocks attached to the regulated abatement work area. (2) Location. The remote personal decontamination system shall be constructed as close to the regulated abatement work area as physically possible. If the remote personal decontamination system must be located at the exterior of the building/structure due to space or code restrictions, it shall be constructed within 50 feet of the building/structure exit used for access by the asbestos abatement contractor personnel. The decontamination unit shall be cordoned off at a distance of 25 feet to separate it from public areas. (3) Airiocks. At a minimum, two (2) extra airlocks as defined in Section 56- 2.1 shall be constructed as per Section 56-7.5(b)(11). One shall be constructed at the entrance to the equipment room or equipment/washroom. The other extra airlock shall be constructed at the entrance to the containment or regulated abatement work area(s). These airlocks shall have lockable doorways at the entrance to the airlock from uncontaminated areas. These airlocks shall be cordoned off at a distance of twenty-five (25) feet and appropriately signed in accordance with Section 56-7.4(c). Airlocks shall not be used as a waste decontamination area and shall be kept clean and free of asbestos containing material. (4) Designated Pathway. The walkway from the regulated abatement work area to the personal decontamination system or next regulated abatement work area shall be cordoned off to delineate it from public areas while in use during Phase HA through HD. (5) Travel Through Uncontaminated Areas. If at any time a worker must travel through an uncontaminated area to access the personal decontamination area, the worker shall HEPA-vacuum and/or wet wipe his/her outer protective clothing while in the regulated abatement work area, then proceed into the airlock, which serves as a changing area, where he/she shall remove the outer clothing and don a clean set of protective clothing. The worker may then proceed to the personal decontamination system enclosure only along a designated pathway as described above. Travel in any other area shall not be allowed. (6) Removal. The remote personal decontamination unit shall be removed only after satisfactory clearance air sampling results have been achieved.

12 NYCRR56 Subpart?, Page 55

CITY_21MC100_003235075

NYC-WTC_000233341

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000233341Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

No available related records indexed in this group.

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000127792 · Box DEP Box 52

NYC DEP Asbestos Project Notification form for abatement activities at a facility in the Phase 1 Decontamination Plan binder.

Similar indexed content

Compare copies and versions →