FEBRUARY 16, 1999
Add 50 KV.A UPS system with 20 minute battery supply. An $' x 9' room with conditioned air
will be required tm house this equipment. A feeder from the UPS to the panel presently provided
for the AV equipment will be required. Wire UPS to all AV equipment. Provide a 2 ton water
cooled DX unit supplied by emergency power. Exact location of UPS and A/C unit has not yet
been determined.
XC\WIAFILES\MMTM0216,G0)
Cees seine Chrys New York Chisnelea When are
NYC-WTC_000173943
OCR can misread numbers and units. Confirm readings against the page image before using them.
NYC-WTC_000173943Source: NYC Law Department, mirrored locally
Job memorandum approving mechanical drawings for FDNY project with requested corrections including diffuser construction details and exhaust fan provisions.
Fax transmission of a revised proposal document regarding architectural and engineering design services for the Mayor's Office of Emergency Management.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.924
Document listing items requiring correction following site inspections of the 23rd floor at 7 World Trade Center for the Mayor's Office of Emergency Management on June 22-23, 1999.
1 shared topics · Same agency, volume and box · similarity 0.923