AMBASSADOR CONSTRUCTION CO, INC.
November 13, 1998
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE; Mayor’s Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Change Order #026
Arab. JofcL# 557-5175
Dear Mr. Weems;
We are pleased to submit herewith our change order #026 to perform the following work at
the above referenced premises for the sum of TWELVE THOUSAND F IVE HUNDRED
NINETY NINE DOLLARS ($12,599.00);
SCOPE OF WORK
As per Swanke Hayden Connell’s sketches FSK-37, 38, 12 and 40, the following is the
cost breakdown;
Drywall
- Close Door opening
- Scar patch after demolition
- Patch electrical outlets in room #23-07 $850.00
Ceilings
- Patch ceiling after demolition $850.00
Electrical
- Add 3-way switches
- Relocate devices in room #23-07
- Add outlets in room #23-11, separate circuit for refrigerator $2,269.00
Appliances
- Add sub-zero refrigerator $1,125.00
Forward. . .