A/V system proposal from Verrex Corporation, May 1998 · Box 7DCASNYC-WTC_000172894
Proposal from Verrex Corporation dated May 18, 1998 to supply audio-visual systems for the Mayor's Office of Emergency Management at 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.940
Fax cover sheet from audio visual company, Aug 21 1998 · Box 7DCASNYC-WTC_000172067
Fax cover sheet from an audio-visual company dated August 21, 1998.
1 shared topics · Same agency, volume and box · similarity 0.930
Credit change order 7 for 7 WTC, September 1998 · Box 7DCASNYC-WTC_000173847
Revised credit change order for fiber distribution system and equipment work at 7 WTC Mayor's Office Emergency Management space.
Same agency, volume and box · similarity 0.906
Cirocotozzi & Co. estimate form, undated · Box 7DCASNYC-WTC_000173258
An estimate form from Cirocotozzi & Co. listing qualifications and exclusions for construction work at a specific location.
1 shared topics · Same agency, volume and box · similarity 0.905
Credit change order #7, September 1998 · Box 7DCASNYC-WTC_000173187
Memo regarding a revised credit change order for fiber distribution work at the Mayor's Office of Emergency Management.
Same agency, volume and box · similarity 0.904
Credit Change Order #7 Memo, 7 World Trade Center, Sept · Box 7DCASNYC-WTC_000168674
Memo submitting revised Credit Change Order #007 for fiber distribution system deletions at the Mayor's Office of Emergency Management.
Same agency, volume and box · similarity 0.902
Memo regarding audio-visual bid package, April 1998 · Box 7DCASNYC-WTC_000172880
Memo dated April 29, 1998 detailing an additional $228,250 cost for audio-visual installation at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.896
Credit change order #7, September 1998 · Box 7DCASNYC-WTC_000173189
Letter submitting credit change order #7 reducing costs by $270,023 for fiber distribution system work at the Mayor's Office of Emergency Management.
Same agency, volume and box · similarity 0.893
Credit Change Order #7 for fiber distribution system, 7 WTC, · Box 7DCASNYC-WTC_000173849
Ambassador Construction submits a credit change order to reduce costs for the fiber distribution and intercom system at 7 World Trade Center.
Same agency, volume and box · similarity 0.893
Request for cost reduction proposals on cabling work, June 1998 · Box 7DCASNYC-WTC_000173397
DCAS requests proposed cost reductions for cabling and conduit work at the Mayor's Office of Emergency Management renovation.
Same agency, volume and box · similarity 0.892
Security system specification excerpt, May 1998 · Box 7DCASNYC-WTC_000173219
Technical specification document detailing end-of-line resistor wiring requirements for the Mayor's Office of Emergency Management security system.
Same agency, volume and box · similarity 0.891
Request for cost reductions on 7 WTC project, June 1998 · Box 7DCASNYC-WTC_000173394
Department of Citywide Administrative Services requests proposed cost reductions for specific work items including cabling and conduit substitutions.
Same agency, volume and box · similarity 0.890