Document / 2 pages
Network infrastructure installation schedule, Mayor's Office, 1998
Machine-extracted title · confidence 90%Memo detailing the schedule for cable delivery, pulling, termination, and testing for the Mayor's Office network infrastructure.
NYC-WTC_000173801–000173802Folder label: “Mayor's Office of Emergency Management ®Job# 867-5176 Time Line”
More like this page
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Network infrastructure timeline memo, July 1998 · page 1 · Box 7DCASNYC-WTC_000166772
Memo outlining the construction schedule and timeline for network infrastructure installation on the 23rd floor at 7 World Trade Center.
Similarity score 0.973 (not a probability)
Minutes of consultant meeting #15, 7 WTC, Oct 27 1998 · page 1 · Box 7DCASNYC-WTC_000173723
Meeting minutes from October 27, 1998, for the Mayor's Office of Emergency Management project at 7 World Trade Center.
Similarity score 0.941 (not a probability)
Project directive for 7 World Trade Center restoration, Feb 9, · page 1 · Box 7DCASNYC-WTC_000173961
Directive to incorporate monitor restoration, food service equipment, and UPS protection into the 7 World Trade Center project.
Similarity score 0.940 (not a probability)
Consultant meeting minutes #18, Nov 1998 · page 1 · Box 7DCASNYC-WTC_000166699
Minutes from the 18th consultant meeting at 7 World Trade Center dated November 24, 1998.
Similarity score 0.940 (not a probability)
Generator installation proposal, 7 World Trade Center, April 1998 · page 3 · Box 7DCASNYC-WTC_000172137
Contractor submits a $717,890 proposal to install generators and related equipment for the Mayor's Office of Emergency Management.
Similarity score 0.939 (not a probability)
OEM memo on WTC EOC restoration, Feb 9 1999 · page 1 · Box 7DCASNYC-WTC_000172228
February 9, 1999 memorandum from the Mayor's Office of Emergency Management detailing restoration and equipment orders for 7 World Trade Center.
Similarity score 0.939 (not a probability)