Project timeline notes for IT infrastructure at 7 WTC, Nov

Machine-extracted title · confidence 90%

List of scheduled tasks including rack building, power availability, and workstation installation dates for the data center.

NYC-WTC_000173732

Folder label: “OEM at 7 WTC

Page image
Scanned page image, NYC-WTC_000173732
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document COSENTINI ASSOCIATES LLP @002 11/10/98 TUE 09:52 FAX ,212 615 3700 COSEN I INI ASSOCIATES LLP ■ TWO PENN. PLAZA, NEW YORK, NY 10121 ■ 2)2-615-3600 > FAX 212-615-3700

JOB MEMORANDUM

TO: Mr. .1. Ma) J a SUBJECT: OEM at 7 WTC

FROM: Vai I.emeshev JOB NO: 1854

CC: DATE: November 10, 1998

Please be advised, space .south from the water storage tank room on the 7th floor is used for the outside air intake to the emergency generators and cannot be utilized for storage.

Area to be cleared to prevent any restrictions to the air flow.

X:\WP\FILF..S\I85'I.98\VI.EK1110..M01

NYC-WTC_000173732

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000173732Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →