NYC Office or Emergency Management
Work completion required for Motorola to start Installation
23 Floor:
• Electrical Riser to Equipment room 11/10/98
• Air-conditioning 11/10/98
• Raised Floor 11/13/98
• Painting 11/13/98
• Room construction 11/13/98
Roof Shelter and Antenna Mi jng:
• Approve mounting details for 31 antennas 9/1/98 .
• Complete I - Beam mounting for antennas 10/15/98
• Grounding for roof area antennas/Shelter 10/15/98
• Electrical riser to shelter 10/15/98
• Complete radio room construction 10/15/98
• Complete Air conditioning 10/30/98 fl/fi
• Complete painting 11/1/98 4^
• Complete Riser for the radio cables to 23 fl 11/1/98 ^7/^
2 LaFavette « Radio Room & Roof Antenna Mounting:
• Approve mounting details for 19 antennas 10/15/98
• GrouniJing for roof area antennas 11/15/98
• Grounding for Radio Room 11/15/98
• Electrical riser to shelter 11/15/98
• Complete radio room construction 11/15/98
• Complete Air conditioning 11/15/98
• Complete Painting n/1/98
Robert B. Hudson 9/28/98
JU. 22 1999 0g:49 2129499762 PflCE.10
JUL 25 1998 17:21 2129499762 fVCE.BB
'oct 19 1998 13=56 2129499762 PAGE.10
NYC-WTC_000173665
OCR can misread numbers and units. Confirm readings against the page image before using them.