NYC 9/11 Public Portal Document
AMBASSADOR CONSTRUCTION CO, INC.
0 June 11,1998
Mr. Walter Weems
Silverstein Properties. Inc.
7 World Trade Center
New York. NY 10048
RE: Mayor’s Office of Emergency Management
7 World Trade Center
Hurricane Wall
Dear Mr. Weems:
We are pleased to submit herewith or budget estimate to construct the “Hurricane Wall" in
accordance with Swanke Hayden Connell Architects’ fax message of 5/27/98 for the sum
of FOUR HUNDRED SEVENTY THREE THOUSAND EIGHT HUNDRED SEVENTY
DOLLARS ($473,870.00):
SCOPE OF WORK
This budget estimate is for changes in the walls over and above the original walls shown on
Addendum 1 drawings dated 5/15/98. We have included the appropriate credits for the
original carpentry and drywall, hollow metal, hardware and special doors which were part
of our original quotation. Our original quotation had included $8,500 for waterproofing
between the curtain wall and the hurricane wall, this value has not been affected by the
change.
The trade value breakdown is as follows:
Demolition (fireproof removal) $5,000.00
Drywall & Carpentry 224.000.00
Hollow Metal <1.756.00>
Finish Hardware <2.800.00>
Electric 20.000.00
HVAC 59.100.00
Iron & Steel 41.600.00
Special Doors <1.822.00>
Blast Proof Doors & Access Doors 60.500.00
Fireproofing 5.000.00
General Conditions 8% 32.706.00
Overhead & Fee 6% 26.492.00
Insurance 1.25% 5.850.00
Total $473,870.00
Continued.../
317 MADISON AVENUE, NEW YORK, NY 10017, 212 922 1020, FAX 212 949 9762
NYC-WTC_000173358
OCR can misread numbers and units. Confirm readings against the page image before using them.