Cost breakdown as 3/9/99 Breakdn2
OEM
7 World Trade Center
% Cost to date
Cost breakdown, including change orders, Total Estimated by trade to the
some of which are still in the review process Construction total estimated
as 3/5/99 Cost todate Cost Budget budget
General Construction $5,644,686 $5,876,651 39.51
Mechanical________ $2,132,198 "$2,219,820 14.92
Electrical_________ $5,305,019 $5,523,025 37.13
Plumbing/ sprinklers $642,104 $668,490 4.49
Subtotal $13,724,007
Landlord Contribution $1,668,858
City's Cost to date $12,055,149
Construction Cost Budget $14,287,986 96.05