Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 · Box 7DCASNYC-WTC_000172054
Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.919
HVAC construction estimate, 7 World Trade Center, Sept 1990 · Box 7DCASNYC-WTC_000173169
Faxed estimate from HVAC contractor for construction work at 7 World Trade Center facility, dated September 1990.
1 shared non-person entities · Same agency, volume and box · similarity 0.903
Bulletin #1: Port Authority comments on MOEM work, undated · Box 7DCASNYC-WTC_000173279
A document listing Port Authority comments and associated cost adjustments for the Mayor's Office of Emergency Management renovation.
1 shared topics · Same agency, volume and box · similarity 0.895
Bulletin #1 regarding Hurricane Wall work at 7 World Trade · Box 7DCASNYC-WTC_000173408
Bulletins detailing costs for hurricane wall construction, column reinforcement, and sheetrock installation at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.892
Letter regarding OEM Bulletin #1 sheetmetal work, Aug 24 1998 · Box 7DCASNYC-WTC_000172081
Letter detailing costs for sheetmetal mechanical labor and materials.
Same agency, volume and box · similarity 0.892
Electric unit heaters quote, 7 WTC generator room, Jan 2000 · Box 7DCASNYC-WTC_000171510
Quote for two 25 KW electric unit heaters for 7 World Trade Center generator room priced at $3,100.
1 shared topics · Same agency, volume and box · similarity 0.885
Revised Change Order #004, 7 World Trade Center, Sept 1998 · Box 7DCASNYC-WTC_000173445
Ambassador Construction submits revised change order for electrical and concrete work at 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.884
Fax cover sheet from Ambassador Construction, Nov 1996 · Box 7DCASNYC-WTC_000171963
Facsimile transmission cover sheet from Ambassador Construction Company dated November 30, 1996.
1 shared topics · Same agency, volume and box · similarity 0.883
Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 · Box 7DCASNYC-WTC_000172034
Cost comparison table for Hurricane Wall work items under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.
Same agency, volume and box · similarity 0.882
Letter re: OEM estimate response, June 1998 · Box 7DCASNYC-WTC_000173319
Letter from Ambassador Construction responding to the Division of Citywide Administrative Services regarding project estimates.
1 shared topics · Same agency, volume and box · similarity 0.882
Correspondence re: Mayor's Office at 7 WTC, June 1998 · Box 7DCASNYC-WTC_000173121
A letter from a contractor to the Department of Citywide Administrative Services regarding work at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.882
Letter regarding Change Order #004, August 1998 · Box 7DCASNYC-WTC_000173453
Letter from Ambassador Construction submitting Change Order #004 for concrete and electrical work at 7 World Trade Center.