← Document results/7DCAS/Change Orders #1, for furnishing and installing sheetrock wall offset on the 23 rd floor to clear return air duct at 7 World Trade Center, New York, N.Y. Contract # 01598F2654
Document / 1 page

Change Order #1 approval for sheetrock wall offset, 7 World

Machine-extracted title · confidence 50%

DCAS letter approves a revised cost of $7,000 for Change Order #1 to install a sheetrock wall offset on the 23rd floor.

NYC-WTC_000171995

Folder label: “Change Orders #1, for furnishing and installing sheetrock wall offset on the 23 rd floor to clear return air duct at 7 World Trade Center, New York, N.Y. Contract # 01598F2654

Page image
Scanned page image, NYC-WTC_000171995
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICES DIVISION OF REAL ESTATE SERVICES MUNICIPAL 8L1LOING Room 20333 NEW YORK. N Y 10007 (212)669-3643 Fix (212)669-2666

WILLIAM J. DIAMOND LORI FIERSTEIN Commissioner Depu/x Cotn/ntsstoncr

August 11th, 1998

Ms. Catherine T. Giliberti Re: Change Orders #1, for furnishing and installing sheetrock Silverstein Properties, Inc. wail offset on the 23 rd floor to clear return air duct at 7 World Trade Center 7 World Trade Center, New York, N.Y. New York, New York 10048 Contract #01598F2654

Dear Ms. Giliberti:

We write with respect to the above referenced change order proposal submitted by Ambassador Construction Co. dated July 28, 1998 in the amount of $10,817.00.

The change order has been reviewed and has been negotiated and approved, subject to audit, in the amount of $7,000 all inclusive.

The Following is a breakdown of the project's budget;

Construction cost Budget $14,287,986.00 Less Landlord's Contribution $ 1,668,858.00 Maximum City Construction Cost $12,619,128.00

Total Construction Cost approved on July 8 $12,982,303.00 Less Landlord's Contribution $ 1,668,858.00 Amount Payable by City $11,313,445.00 Cost Approved this change order $ 7,000.00 Total Construction cost to date $11,320,445.00

Balance remaining in Budget $ 1,298,683.00

If you have any questions please call Glenn Pymento at 212-669-8094 or myself at 669-8086. Thank you for your cooperation.

ini

;xecutive Director of Space Design/DRES

cc: G.Pymento, DRES V.Castagnola, DRES J. Domingvez, DRES J.Menasce, DRES W. Weems, Silverstein Properties Inc.

NYC-WTC_000171995

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000171995Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Change Order #21 transmittal, 7 WTC, Oct 1998 · Box 7DCAS

NYC-WTC_000173818

Letter submitting Change Order #21 for structural work at the water tank and switch gear areas on the 7th floor of 7 World Trade Center.

1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.943

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000167188 · Box 7DCAS

Letter approving Change Order #1 for furnishing and installing a sheetrock wall offset on the 23rd floor to clear return air ducts.

Filed in the same folder

NYC-WTC_000171881 · Box 7DCAS

Letter submitting Change Order #47 for stainless steel generator flexes to address height restrictions at 7 World Trade Center.

Similar indexed content

Compare copies and versions →