. 12/23/9lS 17:52 FAI 2122190256 SWANKE HAYDEN CONNELL 1^1002/002
SENT BY; 12-23-98 ; 2:24PM ; CANTOR SEINUK' GROLP^ 2190059;# 2/ 2
•• THE CANTOR SEINUK GROUP P.C.
GOO MAOtSON AVENUE • NEW YORK. NEW YORK 10082 • TEL (212) 755-4242 . FAX (212) 732-6024
MEMORANDUM
Date: December 23,1998
Project; OEM
Seven World Trade Center
To: Juan Mejia
Swanke Hayden Connell Arch.
From: Anca Baron
Subject: First floor - rebars
As per our sketch SKS-FS-7, dated 10-15-98, all the rebars cut, during the chopping of
the existing first floor slab, must be restored via a min. 3” overlap weld or a cadweld
device. This is necessary for the slab to perform as initially designed.