CO# Description Amount Amount
Requested Approved
83 Modify existing duct work conflicting with $ 2,805.00 $ 2,600.00
the light fixtures
84 Credit for elimination of 8 TV monitor, wall ($30,681.00) ($ 30,681.00)
wash fixture
91 F&I Pump w/funnel drain $ 6,565.00 $ 6,000.00
92 F&I 1 kindoff in press room $ 380.00 $ 380.00
95 F&I three new receptacles under conference $ 1.046.00 $ 1.046.00
room table in Mayor’s Conference room
TOTAL $ 1,692.00 ($ 419.00)
In view of the foregoing, a credit amount of ($419.00) is hereby approved, subject to
audh for the above change orders.
The following is a breakdown of the project’s budget.
Construction Cost Budget $ 14,287,986.00
Construction Cost Budget (Revised) $ 14,287,986.00
Less Landlord’s Construction $ 1,668.858.00
Maximum amount Chargeable to City $ 12,619,128.00
Construction cost approved on 6/2/98 $ 12,864,619.00
Amount approved by CO on 7/8/98 $ 117,684.00
Amount approved by CO on 8/11/98 $ 7,000.00
Amount approved by CO on 9/14/98 $ 102,705.00
Amount approved by CO on 9/21/98 $ 28,442.00
Amount approved by CO on 10/22/98 $ 26,483.00
Amount approved by CO on 10/30/98 $ 42,887.00
Amount approved by CO on 12/01/98 $ 125,453.00
Amount approved by CO on 12/29/98 $ 27,821.00
Amount approved by CO on 1/4/99 $ 3,941.00
Amount approved by CO on 1/25/99 $ 78,288.00
Amount approved by CO on 2/10/99 $ 22,721.00
Amount approved by CO on 3/11/99 $ 220,262.00
Amount approved by CO on 3/25/99 $ 4,874.00
Amount approved by CO on 4/8/99 $ 85,000.00
Amount approved for fuel oil line $ 130,000.00