November 22, 1999
Ms. Catherine T. Giliberti
Silverstein Properties, Inc
7 World Trade Center
New York, New York 10048
Re: Change Order # 105
Mayor’s Office of Emergency Management
7 World Trade Center
New York, New York
Dear Ms Giliberti:
We write with reference to CO # 105 submitted by Ambassador Construction Company on
11/19/1999 in the amount of $136,001.00 for the supply and installation of audiovisual system for the
Library and head end expansion as per drawings AV-1 & AV-2.
The change order has been reviewed and the cost has been found to be reasonable. Therefore, an
amount of $ 136,001.00 is hereby approved , subject to audit, for the change order.
The following is a breakdown of the project’s budget:
Construction Cost Budget $14,287,986.00
Construction Cost Budget (revised) $14,287,986.00
Less Landlord’s Construction $ 1,668,858.00
Maximum amount Chargeable to City $12,619,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $ 117,684.00
Amount approved by CO on 8/11/98 $ 7,000.00
Amount approved by CO on 9/21/98 $ 102,705.00
Amount approved by CO on 10/22/99 $ 28,442.00
Amount approved by CO on 10/30/98 $ 42,887.00
Amount approved by CO on 12/01/98 $ 125,453.00
Amount approved by CO on 1/4/99 $ 3,941.00
Amount approved by CO on 1/25/99 $ 78,288.00
Amount approved by CO on 2/10/99
■ $
22,721.00
Amount approved by CO on 3/11/99 $ 220,262.00