AMBASSADOR'CONSTRUCTION CO, INC.
0 B^EOVEIr^
January 28, 1999
Mr. Walter Weems
Silverstein Properties, Inc.
R Fei > 1 1999
7 World Trade Center
New York, NY 10048
RE: Mayor’s Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Change Order #062
Amb. Job # S54-5175
Dear Mr. Weems:
We are pleased to submit herewith our change order #062 to perform the following work at the
above referenced premises for the sum of NINE THOUSAND SIX HUNDRED SEVENTY
NINE DOLLARS ($9,679.00):
SCOPE OF WORK
As per Swanke Hayden Connell’s memo, roofing details at new curb from Kemper. This work
has been completed as per Kemper detail D-2 .
The cost for this work is as per Benjamin Maintenance’s Invoice #3159 (attached).
Cost of Work $8,350.00
General Conditions 668.00
Overhead & Fee 541.00
Insurance 120.00
Total $9,679.00
Please issue to us a change order for this work.
Very truly yours,
BSADOR C/N^RUCTION CO., INC.
Martin Schneider
Vice President
MS:ag
cc: Juan Mejia - SHC
Glenn Pymento - DCAS
Accepted: Dated:
c:\wpdocs\oem\cos[oemco62.wpd]
317 MADISON AVENUE, NEW YORK, NY 10017, 212 922 1020, FAX 212 949 9762