;UL 31 '90 10:39 rp AhBASSADCR CONSTR. C0212 94'3 9762 TO 9693640 P.02/03
AMBASSADOR CONSTRUCTION CO., INC.
July 31,1998
Mr. Walter Weems
Silverstein Properties, Inc
7 World Trade Center
New York, NY 10048
RE; Mayor’s Office of Emergency Management
7 World Trade Center -1. 7, & 23rd Floors
Change Order #002
Amb. Job #857-5175
Dear Mr. Weems:
We are pleased to submit herewith our change order #002 to perform the following work at the
above referenced premises for the sum of NINE THOUSAND EIGHT HUNDRED EIGHTEEN
DOLLARS ($9,818.00):
SCOPE OF WORK
As per revised specifications from Cosentini (attached) for the (2) Baltimore Air Coil circuit
cooling towers, the pan construction was changed from galvanized steel to stainless steel.
Breakdown of costs:
(2) units $8,470.00
Genera! Conditions 678.00
Overhead & Fee 549.00
Insurance .12UQD
Total $9,818.00
Please notify us if we are to proceed with this work.
We trust the above meets with your approval and we look forward to the continued pleasure of
serving you.
Very truly yours,
CONS'
Martin Schneider
Vic© President
cc; Glenn Pymento
Accepted: Dated:
MS:ag
c-*i«3(toc9>oe(TiloemcoJ wpd]
317MAOISON AVENUE. NEW YORK NY 10017, 212 922 1020. FAX 212 949 9762
NYC-WTC_000168696
OCR can misread numbers and units. Confirm readings against the page image before using them.