NYC 9/11 Public Portal Document
Silverstein Properties, Inc
ill / World Trade Center
New York, N.Y, 1004b
telephone: ?1?-6l9-6669
Fax:
December 9, 1998
Mr. Glenn Pymento
Department of City Wide Administrative Services
Division of Real Estate Services
1 Centre Street, DRES - Room 2000 North
New York, New York 10007
RE: 7 World Trade Center
Mayor's Office of Emergency
Management-V‘, 7'^ & 23"^ Floors
Change Order #2G Revised______
Dear Mr. Pymento:
Attached please find change order #26R in the amount of $12,599.00 submitted by
Ambassador Construction for the following scope of work:
As per Swanke Hayden Connell's revised sketches FSK-12, and 40 dated 11/2/98 and FSK-
43 dated 11/24/98. The following is the cost breakdown;
Drywall
- Close door opening
- Scar patch after demolition
- Patch electrical outlets in Room #23-07 $850.00
Ceilings
- Patch ceiling after demolition $850.00
Electrical
- Recircuit lights, relocate switch, delete $600.00
switch
- Relocate devices in Room #23-07 $300.00
- Add outlets in Room #23-11, separate $1,369.00
circuit for refrigerator
Appliances
- Add sub-zero refrigerator $1,125.00
Woodwork
- Furnish and install new cabinets and
countertops in Room #23-11 $5,775.00
Subtotal $10,869.00
General Conditions $870.00
Overhead and Fee $704.00
Insurance $156.00
Total $12,599.00
NYC-WTC_000168603