January 11, 1999
Mr. Glenn Pymento
Department of City Wide Administrative Services
Division of Real Estate Services
1 Centre Street, DRES - Room 2000 North
New York, New York 10007
RE: 7 World Trade Center
Mayor's Office of Emergency
Management-V', 7‘\ & 23'*^ Floors
Change Order #49________
Dear Mr. Pymento;
Attached please find change order #49 in the amount of $6,779.00 submitted by
Ambassador Construction for the following scope of work as per Swanke Hayden Connell's
memo dated 1/6/99:
Provide ceiling tiles in existing press room grid and relocating sprinkler heads with flush
type heads and caps.
-Ceiling $2,768.00
-Sprinkler $2,880.00
-Black cover plate $200.00
-Subtotal $5,848.00
-General Conditions $468.00
-Overhead and Fee $379.00
-Insurance moQ
Total $6,779.00
If this meets with your approval, please sign and return to my office. Thank you.
Sincerely,
Walter J. Weems III
Building Manager
cc: Cathy Giliberti
Chi Chu
Bill Dacunto
Richard Ramos (DCAS)
Josep Domingvez (DCAS)