Change Order #059 memo, 7 WTC, Jan 1999

Machine-extracted title · confidence 100%

Memo from Ambassador Construction submitting Change Order #059 for $10,948 to install a duplex circuit and drag line on the first floor of 7 World Trade Center.

NYC-WTC_000168519

Folder label: “Change Order #059 Ambassador Construction

Page image
Scanned page image, NYC-WTC_000168519
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

JON 25 ’99 16:17 PR RMBASSRDOR CONSTR. C0212 949 9762 TO 7325190 P.02/02

AMBASSADOR CONSTRUCTION CO. INC

♦ January 25, 1999

Mr. Walter Weems p rEOS OVE JAN ,? 6 1939 I Silverstein Properties, Inc. 7 World Trade Center New York, NY 10048

RE. Mayor's Office of Emergency Management 7 World Trade Center -1, 7 & 23rd Floors Change Order #059 Amb. Job # S57r5175

Dear Mr Weems;

We are pleased to submit herewith our change order #059 to perform the following work at the above referenced premises for the sum of TEN THOUSAND NINE HUNDRED FORTY EIGHT DOLLARS ($10,948.00):

SCOPE OF WORK In accordance with Cosentini Associates' memo dated 1/22/99, furnish and install (1) duplex separate circuit on rack near column #42 on 1st Floor The 4" conduit that is being used for the fiber cable will be used. A new drag line will have to be snaked through the existing conduit The access for the 4" conduit will be on 7th Floor

Electrical Cost $9,445 00 General Conditions 756.00 Overhead & Fee 612.00 Insurance 135.00 Total $10,948.00

Please notify this office if we are to proceed with this work

Very truly yours,

iQ^CONS' ION CO..

Martin SchnjelSer Vice President

MS:ag cc; Juan Mejia - SHC Glenn Pymento - DCAS

Accepted: ______ Dated; c.^pdocs\oem\cos[OGmco59 wpo)

317 MADISON AVENUE. NEW YORK. NY 10017. 212 922 1020. FAX 212 949 9762

** TOTAL PAGE.02 **

NYC-WTC_000168519

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000168519Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Change Order #56 submission, Jan 1999 · Box 7DCAS

NYC-WTC_000172220

Letter from Ambassador Construction submitting Change Order #56 for electrical outlet installation at 7 World Trade Center.

2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.962

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000171403 · Box 7DCAS

Contractor submission for change order covering installation of a duplex circuit and conduit snaking on the first floor.

Similar indexed content

NYC-WTC_000168527 · Box 7DCAS

Memo submitting Change Order #056 for outlet installation and grounding work at 7 World Trade Center.

Similar indexed content

NYC-WTC_000172220 · Box 7DCAS

Letter from Ambassador Construction submitting Change Order #56 for electrical outlet installation at 7 World Trade Center.

Similar indexed content

NYC-WTC_000168587 · Box 7DCAS

Contractor submission for change order to terminate fiber optic cables and install patch panels at 7 World Trade Center.