January 27, 1999
Mr. Glenn Pymento
Department of City Wide Administrative Services
Division of Real Estate Services
1 Centre Street, DRES - Room 2000 North
New York, New York 10007
RE: 7 World Trade Center
Mayor's Office of Emergency
Management-V', 7*'’, & 23"* Floors
Change Order #60 _____
Dear Mr. Pymento:
Attached please find change order #60 in the amount of $8,114.00 submitted by
Ambassador Construction for the following scope of work:
As per Swanke Hayden Connell's sketch FSK-54 to close gap at steel in hurricane wall with
16 gauge steel plate. The cost is as follows:
Labor $5,500.00
Material $1,500.00
Subtotal $7,000.00
General Conditions $560.00
Overhead and Fee $454.00
Insurance $100.00
Total $8,114.00
If this meets with your approval, please sign and return to my office.; Thank you.
Sincerely,
c < 'c y c. U t/T z c,
Walter J. Weems III
Building Manager
cc: Cathy Giliberti
Chi Chu
Bill Dacunto
Richard Ramos (DCAS)
Josep Domingvez (DCAS)