← Document results/7DCAS/Mayor's Office of Emergency Management 7 World Trade Center - 1, 7 & 23rd Floors Change Order #066 Amb. Job # S57-5175
Document / 2 pages

Change Order #66 for floor boxes, 7 WTC, Feb 1999

Machine-extracted title · confidence 95%

Memo submitting Change Order #66 for $15,460 to install floor boxes and relocate wiring at 7 World Trade Center.

NYC-WTC_000168493–000168494

Folder label: “Mayor's Office of Emergency Management 7 World Trade Center - 1, 7 & 23rd Floors Change Order #066 Amb. Job # S57-5175

Page image
Scanned page image, NYC-WTC_000168494
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

FEB 01 ’99 10:19 FR PMBflSSfiDOR CONSTR. C0212 949 9762 TO 7325190 P.03Z07

AMBASSADOR CONSTRUCTION CO. INC

Mr. Walter Weems February 1, 1999

Page Two...

Flooring Furnish and install new base and flooring around raised floor $300.00

Subtotal $13,338.00 General Conditions 1,067.00 Overhead & Fee 864.00 Insurance 191.00 Total $15,460.00

Please notify us if we are to proceed with this work.

Very truly yours,

AMBASS/yOOR INSTRUCTION CO , INC.

Martin Schneider Vice President

MSag

cc: Juan Mejia - SHC Glenn Pymento - DCAS

Accepted: Dated: C'iwpaoc5\oem\wjs[oemco00 wpo]

NYC-WTC_000168494

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000168494Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Change Order #66 submission, 7 WTC, Feb 1999 · Box 7DCAS

NYC-WTC_000171455

Ambassador Construction letter dated February 1, 1999, submitting Change Order #66 for $15,460 to install floor boxes and relocate wiring at 7 World Trade Center.

2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.990

machine-extracted · confidence unavailable · Check page ↗
Change Order #26R submission, 7 WTC, Dec 1998 · Box 7DCAS

NYC-WTC_000171810

Letter from Ambassador Construction submitting revised change order #26R for repairs at the Mayor's Office of Emergency Management.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.958

machine-extracted · confidence unavailable · Check page ↗
Change Order #85 submission, 7 WTC, May 1999 · Box 7DCAS

NYC-WTC_000168422

Contractor submits Change Order #85 for $34,401 to install new piping for re-routed fuel oil lines, including masonry work.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.957

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000171455 · Box 7DCAS

Ambassador Construction letter dated February 1, 1999, submitting Change Order #66 for $15,460 to install floor boxes and relocate wiring at 7 World Trade Center.

Similar indexed content

NYC-WTC_000168605 · Box 7DCAS

Submission of Revised Change Order #26R for drywall closure, scar patching, and ceiling work at 7 World Trade Center.

Similar indexed content

NYC-WTC_000171810 · Box 7DCAS

Letter from Ambassador Construction submitting revised change order #26R for repairs at the Mayor's Office of Emergency Management.

Similar indexed content

NYC-WTC_000168609 · Box 7DCAS

Submission of Change Order #26 for closing door openings and patching drywall and ceilings at 7 World Trade Center.

Similar indexed content

NYC-WTC_000168422 · Box 7DCAS

Contractor submits Change Order #85 for $34,401 to install new piping for re-routed fuel oil lines, including masonry work.

Similar indexed content

Compare copies and versions →