NYC 9/11 Public Portal Document
AMBASSADOR CONSTRUCTION CO.. INC.
Mr. Walter Weems
Auguste, 1999 D AUG -9 '^39
Silverstein Properties Inc.
7 World Trade Center
New York, NY 10048
Re; Mayor’s Office of Emergency Management
7 World Trade Center
Change Order #093
Amb. Job #857-5175
Dear Mr. Weems;
We are pleased to submit herewith our change order #093 to perform the following work at
the above referenced premises for the sum of FOUR THOUSAND EIGHT HUNDRED
NINETY TWO DOLLARS ($4,892.00);
In the P.I.U. room wire the 6 shade motor and two switch
controllers with new circuits from panel.
Electrical Cost $3,200.00
Motor Logic Controllers 1,090.00
Subtotal $4,290.00
General Conditions 257.00
Overhead & Fee 273.00
Insurance 72.00
Total $4,892.00
All work to be performed on regular working hours.
Please notify us if we are to proceed.
Very truly yours,
^^SSa/oR CC^S-^UCTI^N co., INC.
•^Martin Schneider
Vice President
cc; Juan Mejia / SHC
Glenn Pymento / DCAS
MS; am
Accepted;______________ Dated;
C.\OFFICE\WPWIN\WP00CS\0EM\C0'S\0EMC093 WPD
317 MADISON AVENUE • NEW YORK, NY 10017-212 922 1020 • FAX 212 949 9762
NYC-WTC_000168394