MEMORANDUM
Date: June 22, 1998
To: Lori Fierstein
Deputy Commissioner/DRES
From: Josep Domingvez
Assistant Director of Spac! RES
Re: Mayor’s Office of Emergency Management
7 World Trade Center
0<t/L /)
New York, New York
Project # 96-134€j(
The following is my explanation, phase by phase, of the circumstances which have caused this
project to fall behind the Project Schedule dated November 14, 1997, issued by the Architect
(SHCA) based on the information supplied to them by Leasing.
This schedule was unrealistic from its inception, it did not allow enough time for MOEM
review/approvals for the Schematic Design phase, or for DCAS & MOEM review of Contract
Documents, and Bidding Phases.
It also did not take into consideration the Port Authority cumbersome bureaucratic procedures.
Another factor to consider is that once the Lease was executed (March 26, 1998) a new schedule
took precedence as dictated by the Lease, which sets different timeframes.