← Document results/7DCAS/Mayor's Office of Emrgeucy Management 7 World Trade Center 1st, 7th, & 23rd Floors NY, NY Project # 96-1346
Document / 3 pages

Construction cost estimate approval documentation, July 1998

Machine-extracted title · confidence 88%

DCAS approval letter and supporting documentation for construction cost estimates for Mayor's Office of Emergency Management at 7 World Trade Center, July 1998.

NYC-WTC_000167191–000167193

Folder label: “Mayor's Office of Emrgeucy Management 7 World Trade Center 1st, 7th, & 23rd Floors NY, NY Project # 96-1346

Page image
Scanned page image, NYC-WTC_000167191
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

JUL-08-98 09 = 24 FROM = 9 ILVERSTEIN PROPERTIES ID:2127321207 PACE 2Z3

DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICE DIVISION OF REAL ESTATE SERVICE MUNICIPAL BUILDING, ■ Room 2053$ NEW WXK. N.Y. 10007 (212)669-3640 F*x (212)669-2666

WILLIAM J. DIAMOND LORIFIERSTEIN Canmarioner £>epaiyCoaaussi0aer

July 2,1998

Ms. Catherine T. Gilbert! Silverstein Properties, Inc. 120 Broadway _ New York, NY 10271

Re: Mayor’s Office of Emergency Management 7 World Trade Center pt, 7tb,&23rd Floors s NY, NY Project #96-1346

Dear Ms. Gilbert!

We thank you for your timely response to the various clarifications/additional inftxination requested by this office with reflect to the construction cost estimates. Listed below is a summary of documentation reviewed to evaluate and approve the work cost

• Original cost estimate dated May 27» 1998 in the amount of $11/123^8.00.

• Revised trade cost dated June 10,1998 including work associated widi addendum 1, in the amount of $11,645,746.00.

• Cost Estimate dated June 11,1998 for additional work related to A.V. equipment in die amount of $34,475.00.

• Cost of using the existing fuel lines in die amount of $302,410.00 dated June 16,1998.

• Tapping cost in the amount of $219,800.00 dated June 12,1998.

• A/E lees proposal in the amount of $91,500.00 dated June 30,1998 this includes reimbursable op to a maximum of $14,750.00.

• Cost estimate incorpmating scope reductions/modifications as requested by diis office dated June 26,1998.

C:silbcni3inoem/9/ip

NYC-WTC_000167191

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000167191Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →