JUL-ee-98 09=24 FROM=SILVERSTEIN PROPERTIES 102127321207 PACE 3Z3
Based on the above the following costs are approved subject to audit.
1. Revised cost bid including addendum 1. $11,645,746-00
2. Additional cost for A & £ contractor. $ 34,475.00
3. Cost to use existing fuel lines. $ 302,410.00
4. Tapping fees (Electrical) $ 219,800.00
5. ATE fees $ 91,500.00
6. Cost of generators approved April 17,1998 $ 717,890.00
7. All scope reductions as per your letter dare June 26,1998 - $ 503388.00
8. Revised “Hurricane Wall” inclusive of upgrading as per
your letter dated June 26,1998. $ 356.186.00
Total - $12,864,619.00
The rpproval ofdie estimate is based on the contractor having visited die space and satisfied himself to
the existing conditions and to die work called for in the drawings and specificatiwi. Therefore, the rmly
change order will be for additional work/scope changes requested in writing by this office.
The following is a breakdown of the project's budget.
Construction Cost Budget $14387,986.00
Landlord's Contribution -$ 1.668.858.00
Maximum City Constructicm Cost $12,619,128.00
Construction cost approved $12,864,619.00
Less Landlord's contributions -$ 1.668.858.00
Amount payable by City $11,195,761.00
Balance remaining in Budget $ 1,423367.00
Thank you ftw your cooperation.
Sil
Executive Director of Space Design
c: Jerry Hauer, OEM Joseph Menasce, DRES
Iris Weinsball, DCAS Josep Domingvez, DRES
Lori Fierstcin, DRES Vinicius Castagnola, DRES
Jeff Koodrai, DRES Gl«in Pymento, DRES
Patrick Ronan, OEM
C:aUbcrti3moeiWjp/ip
NYC-WTC_000167192