0 MINUTES OF CONSULTANT’S MEETING #3
PROJECT: Mayor’s Office of Emergency Management
7 World Trade Center
1, 7, & 23rd Floors
Amb. Job#S57-5175
DATE: August 4, 1998
PRESENT: Martin Schneider Ambassador
Jack Klein Ambassador
Mark Torre Silverstein Properties
Walter Weems Silverstein Properties
Glenn Pymento DCAS
Bob Melaniff DITT
Josep Domingvez DCAS
Patrick Ronan OEM
Steve Harte, Motorola
1. SHOP DRAWING STATUS
- Ambassador advised that the following shop drawings are still out for review:
Electrical - Bus Duct, Cable Tray, Safety Switch
Wood Door Schedule - Swanke advised that this will be rejected
Sprinkler - Inergen System
2. PROJECT STATUS
- Reviewed minutes of 7/28/98.
- Ambassador advised of the following:
1. Layout and stud work is approximately 80% complete. Need approval of hurricane
wall to continue.
2. Electrical riser piping has been distributed from 23rd to 7th Floors. Riser chopping
and coring will continue for the next 6 to 7 weeks.
3. Duct installation is approximately 10% complete.
4. Condenser water piping has started.
5. Plumbing drain work of 22nd Floor to start weekend of 8/9/98.
6. Sprinkler piping to start 8/7/98.
- Concrete curb work for machine room, 23rd Floor to be started next week.
- Ambassador stated that the protection on the 1st Floor for fuel oil tank work is to
begin next week. Ambassador to coordinate with SPI.
- Ambassador stated that 7th Floor work needs to be resolved. SPI stated that they
would resolve this week.