. •' AMBASSADOR CONSTRUCTION CO., INC.
♦
PROJECT:
MINUTES OF MEETING #6
Mayor’s Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Amb. Job #857-5175
DATE: August 18, 1998
PRESENT: Martin Schneider Ambassador
Jack Klein Ambassador
Jay Koven Ambassador
Mark Torre Silverstein Properties
Charlie Magee Silverstein Properties
Walter Weems Silverstein Properties
Tony Rubino Silverstein Properties
Bob Goodyear ABCO-Peerless
Richard Jarde, Gary Fishbone R.B. Samuels
Lloyd Kozel Ace Audio Visual
Joe Mackey Par Plumbing
Joe laquinto Precision Interiors
Donald Murphy Kaback
Joe Amato Newco
Jeff Timberg Superior Acoustics
1 SAFETYREVIEW
- Ensured that all OSHA posters are up in good condition.
- Reviewed fire exits.
- Checked first aid kit(s) and safety manual.
- Reviewed safety procedures (clothing, protective gear, work procedures).
- Checked cleanliness and condition of construction area.
- INQUIRED IF ANY INCIDENTS OR INJURIES OCCURRED WHICH WERE
NOT REPORTED TO PROJECT SUPERINTENDENT. No accidents reported.
- All trades will be responsible for their own safety. Trades will be held to OSHA
standards and any tradesman not conducting work in a safe manner will be told
to leave the project. Any costs or delays will be incurred by the subcontractor.
- Ambassador stated that they have removed ladders that looked unsafe.
- Ambassador stated that they will be issuing a hand-out on site safety issues.
Ambassador also stated that all contractors are responsible for the safety of their
personnel as well as the safety of others on the job.
2. PROJECT SCHEDULE
- Reviewed minutes of 8/11/98.
- Ambassador advised that substantial completion of 23rd Floor will be the first week
of November.
- Ambassador advised that the 7th Floor demising work will be completed by 8/24/98.
- Ambassador advised that the 1 st Floor work will start the week of 8/17/98
Continued.../