V. Scope of Services / Approach TKLP
the * equipment items identified in the RFP. The vendors will be required to submit the
results of their tests and the referenced documentation establishing industry standard
for tolerances. TKLP cannot, at this point, anticipate whether these factory tests will be
successful at the first test or not. TKLP will specify that the vendor will be responsible for
all costs, including engineering attendance costs, if his system or equipment must be
tested the second time. Since TKLP does not work for the vendor, nor does TKLP want to
be dependent upon reimbursement from the vendor. These costs will be reimbursed to
CDCSA. TKLP will bill CDCSA for attendance for more than one test as a change order
and be reimbursed on that basis.
Construction Administration
1. Bid Support — TKLP's project manager will attend a pre-bid meeting with their client.
TKLP's project manager will work with his team to respond to any questions during the
bidding period submitted to him by his client. TKLP will prepare addendum to the bid
documents where necessary. TKLP has anticipated that CDCSA will have a scoping meet
ing with the successful bidders. We anticipate the following disciplines will attend each
of these meetings: HVAC engineer; instrumentation and controls engineer; plumbing
and fire protection engineer; electrical engineer; communication and data cabling engi
neer with our project manager.
2. Schedules — TKLP's specifications for equipment will request schedules from each ven
dor to be submitted when bids are received. TKLP will check these schedules to see that
they coordinate with the contractor's overall schedule. TKLP will require, by specifica
tion, that the contractor provide a schedule for shop drawings. TKLP will review this
schedule in light of the overall construction schedule and comment if they believe the
submitted schedules are inappropriate. TKLP will specify that the contractors provide
detailed schedules for their work and the need for delivered equipment. TKLP will at
tend weekly construction meetings where the contractor, by specification, should review
his schedule, work completed, and work to be done. TKLP will comment where they
believe delivery and installation of the contractor's work is falling behind schedule.
3. Construction Meetings — TKLP will attend those construction meetings when the MEP
work is being installed. TKLP's attendance at this meetings will consist of two people—
a project manager and a selected discipline engineer. We anticipate that the MEP work
will begin being installed February 1,1993, and extend to March 1,1994, which includes
the site commissioning. This includes 13 months or 56 construction meetings.
4. Site Visits and Field Reports — TKLP will visit the site to review the work done. Site
visits will be performed by the appropriate engineer for that disciplines. The site visits
will be performed by individuals from the following disciplines: HVAC; plumbing/fire
Forest City Tech Place Associates for Full Engineering Services 05/06/92 (P237] V-5
NYC-WTC_000166625