DEPARTMENT OF DESIGN AND CONSTRUCTION
DIVISION OF INFRASTRUCTURE
REPORT SUMMARY
GRAND TOTAL OF PROJECTS: 85
GRAND TOTAL OF:
BID AMOUNT: $803,944,797.04
CURRENT AMT: $516,890,585.92
VOUCHEREDAMT: $232,243,544.31
EST FINAL COST: $822,081,973.64
07/05/2011 Notes: (1) CCD includes lOdays for moWlization for all projects. (2) Ths dock tor%tinie elapsed stops at substantial txjmptetion. (3) Delay is flagged if"% Const CompT is more than 20 points below "% Time Elap Orig". PagelTof 17