From: Theodorellys, Penny
Sent: Thursday, February 06, 2003 2:08 PM
To: Radhakrishnan, Krish
Co: Gilsenan, Michael
Subject: 114 Liberty Monitoring Contractor Scope of Work
114 Liberty St
Monitoring 2 6 ...
I have incorporated the changes sent over by Mark and Chuck. I spoke to Chuck regarding the
asbestos sampiing and the flow rate issue they raised. Chuck stated we could leave as is - he didn’t
realize number 2 was “during sampling” and therefore a different set of sampling. The rest of the
comments were fine and I replaced the existing language. We still need to wait on their attachments.
Also, I added the row to Table 1 and referenced the table at both the asbestos and other parameter
sections. Any other comments?
1
NYC-WTC_000155453
OCR can misread numbers and units. Confirm readings against the page image before using them.
NYC-WTC_000155453Source: NYC Law Department, mirrored locally
Request for review of monitoring contractor specifications for air sampling, including sampling methodologies, limits of detection, and clearance criteria, with reference to prior…
Request for review of monitoring contractor specifications for air sampling, including sampling methodologies, limits of detection, and clearance criteria, with reference to prior…