- Contractors requested that they be compensated for the travel time it takes to deliver their
samples to the lab and the cost of sampling cassettes resulting fi-om the large amount of samples
they need to run (#3 Attachment A).
- Contractors requested that they be compensated for their time accompanying their HVAC
subcontractors during field inspections (#4 Attachment A).
- Dealing with F2L and the data base in general is taking much longer than expected. F2L can't be
run on multiple machines and therefore when you have work ongoing in several locations it
creates logistical problems that cost the contractors time. Furthermore, they claim they are
spending at least one hour waiting for F2L to print the chain of custody forms. At the pre bid
meeting they clearly remember being told by us that data base management activities would take
minutes not hours. This is a major issue for them and they are requesting appropriate pricing
adjustments. Furthermore, they believe that data base management is really project management
time (not project monitor) and this position is not provided for under the contract
(#5 Attachment A).
- (Athenica) The quantity of HVAC inspections specified on the bid sheet was 750. Athenica got
a unit price based on this volume of work. Athenica doesn't think they will get the volume of
HVAC inspections in Battery Park City to warrant a low unit cost price from their subcontractor
and as a result are incurring higher unit price costs than anticipated (#6 Attachment A).
- (Athenica) Unanticipated costs associated with faxing, mailing and copying information for
dissemination to residents requesting cleaning or testing (#7 Attachment A).
In addition, there are three (3) pricing issues that are not included in Attachment A but
were discussed during our meeting, they are as follows:
1) EPA has requested that DEP allow the Monitoring Contractors to continue personal
monitoring for another four (4) weeks. This extension is necessary due to the delay in EPA and
OSHA receiving data from the MCs. Also, it was discovered that once the data was submitted it
was PCM only when in fact the contractor was required to submit both PCM and TEM. The
contractors need to be reinstructed by DEP regarding the analysis requirements and OSHA has
requested that they provide additional information regarding work practices during sampling.
2) Compensation for No-Shows - It was agreed that the MCs would be compensated for 4 hours
for “Test Only”and should be notified of such. However, the Cleaning Contractors are concerned
about scheduling issues and cancellations limiting the amount of cleaning conducted to date. They
are worried that if the trend continues they will not recoup the money they laid out for insurance
and equipment. They are requesting 24-36 hour advance notice of scheduled cleaning from the
Project Monitor. Cancellations are also creating problems with their workforce. Workers want a
guaranteed eight hour day. When residents cancel cleaning with less than 24 hour notice workers
3