ADDENDUM #2
World Trade Center Dust Cleaning Program
Monitoring Contract Scope of Work
- Outside air intake louvers, grates and screens
- Outside air duct
— Outside air dampers
- Return air grilles
- Return air plenum
— Return air plenum damper
- Return air ducts
- Turning vanes >
- Mixing chambers
- Filter rack
- Filter banks/media
- Pre-heat coils
- Cooling coils
- Re-heat coils
- Humidification and/or air cleaning equipment
- Fire dampers
- In-line re-heat coils
- Interior insulation
- Duct connectors
- Blower assembly including blower wheel, blower housing, air vanes, in-line noise
attenuators, acoustical treatments (e.g., baffles, duct linings)
- Condensate drain pan
- Condensate accumulator
- Supply air plenum
- Supply air plenum damper
- Supply plenum or supply duct linings
— Supply air ducts (high and low pressure)
- Supply air diffusers
— Terminal boxes
- Open or ducted passive ventilation shafts
6.5 Evaluation Procedures
6.5.1 Accessibility
6.5.1.1 Locate System Components Accessible for Visual Inspection
The HVAC/Electrical Professional shall make an assessment of the accessibility of the various
components of the system. For example, components may be enclosed within permanent sheet
metal panels, or may be located above or behind solid plaster ceilings and walls.
NYC-WTC_000140297
OCR can misread numbers and units. Confirm readings against the page image before using them.
NYC-WTC_000140297Source: NYC Law Department, mirrored locally
Addendum detailing all ventilation system components to be inspected and cleaned, including intake louvers, ducts, coils, blower assemblies, and duct linings at World Trade Center.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.998
Identification of ventilation system components most likely to have WTC-related dust accumulation, including air intakes, dampers, filters, and downstream components.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.938
Addendum detailing all ventilation system components to be inspected and cleaned, including intake louvers, ducts, coils, blower assemblies, and duct linings at World Trade Center.