An ACP7 form signed by the contractor and air-monitoring firm shall be submitted directly to the DEP
representative on site, The DEP shall provide notification to the NYS DOL. The size of the project,
specified arce, shall be indicated on the ACP? form. Building owners shall provide written authorization
to the DEP for the work activities.
DEP wil! coordinate ectivities with building owners and other city agencies.
The sites and specific areas to be cleaned shall be determined and specified by the DEP.
The contractor shall restrict access by the public to the work area (s) during clean-up activities. Caution
tape and warning signs shall be used to identify work areas. Access shall be limited to the contractor, his
employees, and Federal, State or local officials.
Ths contractor shall provide all necessary squipment, to remove, bag, iransport, and dispose collected
waste. The contractor is responsible for supplying all necessary equipment.
The specific clean-up procedures for building roofs are attached. The DEP shall consider substitution of
the specified methodologies only if the request is received in writing. Any substitutions must receive
prior approval by the DEP.
For large asbestos clean-up projects, a partial decontamination system (changing room and shower) shall
be required at an entry/exit fom each work area. A remote decontamination system shall be acceptable
with DEP on-site approval.
The contractor shall have on staff and assigned to the contract a sufficient numbes of properly trained and
certified workers. See above.
Page 2
05/03/02
NYC-WTC_000134069