OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document I'

emru►„ NYC DEPARTMENT OF ENVIRONMENTAL PROTECTION • Asbestos Control Program ' 59-77 JuntIon Boulevard, 8'' Floor, Corona, NY 11368-5107 !6i t*M..J Building Dept. or T FOR OFFICIAL USE ONLY ASBESTOS PROJECT NOTIFICATION WILL BE "`"` (ASBESTOS INSPECTION REPORT) TED .~~., ~.s►Y;,:. 1 (See fee schedule)

When submitting this form at the NYC Department of Buildings, the original form and three (3) copies with original signatures are required. Submittal at the NYCDEP requires one copy of the form with original signatures. This form must be submitted to the NYC DEP not less than one week in advance of the start of abatement activities .

I. FACILITY

2. Address _ 62 WILLIAM STREETL____ _________ Borough Manhattan -- Zip

AKA 30_38 CEDAR STREET- _—_ —_ —_ —_ ___ 3. Block 4. Lot

5. Type of Facility__—_____---__—__—__—___ 6. Name of Building _—_—__—_---_— II. BUILDING OWNER

7. Name BMS REALITY ASSOCIATES __---_—__—__—__—_ 8. Contact Person --_--_ — (212) 809-2371 9. Tel. # ---------------- - Fax # --------------------- i 10. Address ------------------------------ Cityl------------------- State ----- Zip

Ill. GENERAL CONTRACTOR

11. Name----------- ----------- ---- Tel. # ------------------ IV. ASBESTOS ABATEMENT CONTRACTOR TRIO ASBETOS 12. Name _—__ CR __—_ REMOVAL—_ S _________—__________13. Contact Person STEVEN PARMIGIANI OP.

14. Federal Employer ID. # ----__—__—__--_ 15. Tel. # (718) 961_4100-------- Fax #

16. Address 14 - 120 129 STREET -----_--__—_____ City COLLEGE POINT __—__ State ..N'L_ Zip _11356

V. THIRD PARTY AIR MONITOR

17. Name WARREN & PANZER ENGINEERS, P.C. 18. Contact Person MIKE NOLAN

19. Federal Employer ID. # —__—__—__--_—_- 20. Tel. # (212j922_0077 _—__—_ Fax # 212) 922-0630

21. Address 228 EAST 45 STREET--------------- City N.Y State NY— Zip

22. Sample Analysis Laboratory_WARREN & PANZER ENGINEERS, P _C.------ 23. NYS DOH ELAP # 111251

VI. PROJECT INFORMATION 24. Starting date for this portion of work _I_ t) Projected completion date __LJ 1_ Asbestos work schedule 0 Monday 0 Tuesday 0 Wednesday 0 Thursday 0 Friday 0 Saturday.Q.Sunday Shift from: 8:00__ 0 am D pm to 80_0___ D am 0 pm If other, ~~ specify ------------------------------------- -------------- ~ Access to inspect the premises must be provided during the work schedule indicated in this item. ( ( -~/ ~~

25. Total amount of asbestos-containing material to be abated during this work - __ 13,492 Square Feet, and/or —_—_—_ Linear Feet y ACP7

NYC-WTC 000110301

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000110301Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →