New York City Department of Environmental Protection
Bureau of Environmental Compliance
WTC Unoccupied Building Cleaning Program
125 Cedar Street
Scope of Work
Project #WTC_UNC
A MANDATORY PRE-BID meeting is scheduled for August 28, 2002 at 1:00 P.M. at 125 Cedar
Street, Building Lobby, New York, N.Y. This conference will include a walk through of the
entire building.
Background
A follow-up visit to 125 Cedar Street, a.k.a. 110 Liberty Street, revealed debris and significant
dust accumulation present on surfaces throughout the interior of the building. The interior
cleaning is to be accomplished by a licensed asbestos abatement contractor.
Purpose
A New York State Department of Labor (NYSDOL) licensed asbestos contractor with NYC DEP
and NYSDOL certified workers shall perform the clean up of building interiors (12 stories, a
penthouse, and a basement-5,000 to 6,000 square feet per floor). The entire building including
common spaces, storage spaces, residential and commercial spaces (includes retail space on
Liberty Street) shall be included in the clean up activities.
Contract Term
This contract shall be in force for 90 consecutive calendar days from the DEP commencement
date. Contractors must be prepared to mobilize within 72 hours of the contract award.
Scope of Work
kl) All ork perioriued snail ue i❑ compliance with all applicable, relevant, and appropriate
regulations, including but not limited to those of the United States Environmental
Protection Agency (USEPA), the United States Department of Labor, the New York State
Department of Labor (NYSDOL), the New York State Department of Environmental
Conservation, the New York City Department of Sanitation, the New York City
Department of Health (NYC DOH), and the New York City Department of Environmental
Protection (NYC DEP).
(2) An ACP-7 form, asbestos project notification form shall be submitted as required by Title
15, Chapter 1 of the Rules of the City of New York (RCNY), directly to the NYC DEP
Asbestos Control Program prior to the start of work. USEPA and NYSDOL notification
shall be submitted.
(3) A third party air monitoring firm shall perform air sampling and provide project
oversight.
(4) The asbestos contractor shall provide sullicieut equipment and experienced personnel to
complete work area preparation and cleaning activities of the building interiors within three
I of 6