Asbestos abatement schedule memo, 114 Liberty Street, Mar 2003

Machine-extracted title · confidence 100%

Memo outlining the daily asbestos abatement and testing schedule for 114 Liberty Street from March 21 to March 26, 2003.

NYC-WTC_000102577–000102578

Folder label: “SCOPE OF WORK ADDENDUMS WORK SCHEDULE”

Page image
Scanned page image, NYC-WTC_000102577
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

MAR.21.2003 3:50PM ETS INC. NO. 227 P. 2/2

March 21, 2003

Ms. Penny Theodorelllys Asbestos Control Program NYC Department Of Environmental Protection 59-17 Junction Boulevard Corona, NY 11368

Re: Asbestos Abatement Schedule —114 Liberty Street, New Yorkq NY

Note: 114 Liberty Street must be opened at 6:30am and closed at 1:00am each day. Friday, 3/21/03 7:00 am — 3:30 pm Abatement 4:00 pm — 12:30 am Abatement

Saturday, 3/22/03 6:30 am — 7:00 pm Abatement / Phase I Visual Inspection, Sunday, 3/23/03 6:30 am-- 7:00 pm Abatement/Phase I VisuallTesting Monday, ' 3/24/03 7:00 am— 3:30 pm Abatement (Phase II) 4:00 pan —1230 am Abatement (Phase E) Tuesday, 3/25/03 7:00 am — 3:30 pm Abatement (Phase II) 4:00 pm —12:30 am Abatement (Phase 11)

Wednesday, 3/26/03 7:00 am — 3:30 pm -Abatement(Phase 11) 4:00 pm — 12:30 am Abatement/Cleaning (Phase 11) Thursday, 3/27/03 7:00 am — 3:30 pm Phase II Cleaning 4:00 pm —12:30 am Phasc 1I Cleaning Friday, 3/28/03 7:00 am — 3:30 pm Phase II Visual Inspection 4:00 pm-12:30 am Phase II Testing Saturday, 3/29/03 7:00 am — 3:30 pm Demobilize 4:00 pm —12:30 am Demobilize Note: 1. Schedule subject to change if area sequences are switched 2. ETS win reqinr dedicated elevator service each waste out shift 3. Building mu be opened at 6:30am and closed at 1:00ai,i'each day. ,

Shyld you have any questions regarding the above schedule, please. do not hesitate to call.

Inc.

I.obert Middleton Sr. Project Executive PWdm nh'114L be %

NYC-WTC000102577 60 ,---

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000102577Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000102710 · Box DEP Box 35

Header page of a DEP Asbestos Inspection Report submitted by ETS Construction for the 114 Liberty Street site.

Cited alongside this record in an Ask answer

Compare copies and versions →