<agasparro(c~jIcenvironmental.com>; <rmiddleton(c~etsets.net>
Cc: "Gilsenan, Michael" <mgilsenan(a~dep.nyc.gov>;
"Radhakrishnan, Krish"
<kradhakrishnan(a-dep.nyc.gov>
Sent: Monday, April 07, 2003 10:26 AM
Subject: 114 Liberty Street
This is in response to your request to leave the
polyethylene sheeting
over
the windows in place at the completion of the Department's
unoccupied
building clean up of debris from the collapse of the WTC.
It is my understanding that building representatives and
the Department
retained contractor, ETS, were in discussions regarding
this matter prior
to
addressing the request with the Department. I received
the first call and
inquiry while at home on Friday evening (April 4, 2003)
while the
breakdown
was directed to begin at 7:00 a.m. Saturday (April 5,
2003). The two
major
issues are the late request to the Department for the
change in project
planning and the direct communication with the contractor
rather than the
Department. Also, please note the written request was
received on
Saturday,
April 5, 2003 at 9:42 A.M. The request included two
original messages
dated
Friday, April 4, 2003 at 8:35 P.M. and at 9:21 P.M. that
were not
received.
Also, the project monitor, JLC Consultants, did not
receive the
information
regarding the request.
NYC-WTC 000100704