Regulatory Submittal Part II -
Environmental Community Air Monitoring Program
Fiterman Hall — 30 West Broadway
Airtek Project 05-0867 — January 10, 2006
Attachment A
Table 1— Community Air Monitoring
Location Parameter(s) Sample Sample Collection Analysis Method Comment
Frequency Flow Rate and
Duration
Site Area Mercury Each work day Real —Time: 3 site Lumex, portable Lumex results are
tours per work shift mercury analyzer real-time data
logged
Site Area Particulate Continuous during Visual Visual Visual Notations
(Visible dust working shifts Observation on site log
emissions)
Site Perimeter- Particulate Daily Continuous Real- Laser dispersion
four fixed PM-2.5, time data-logging Real time
locations listed PM-10 analysis, Met One
below E-BAM
Site perimeter- Particulate Each work day, Continuous Real- R&P TEOM Comparison data
one of the PM-2.5, rotated bi-weekly time data-logging for E-BAMs.
fixed locations PM-10 to one of the fixed
below reference locations
testing
Station #1: 1. Asbestos 1. ACM each 1. 6.0 LPM/8hr 1. TEM/PCMe Sampling durations
Ground Level work shift, and may be modified
at the each off-day. . based on Site
northwest 2. Mercury 2. Daily 2. 0.4 LPM/24hr 2. EPA Conditions.1
comer of the 324/1631
Building 3. Metals 3. Daily 3.4.0 LPM/24hr 3. ICP/MS
4. Silica 4. Daily 4. 2.0 LPM/8hr 4. XRD
Station #2:
5`h Floor 5. Organics 5. Organics — 5. 200-300LPM 5. PCB (EPA
Setback Roof Weekly 2 TO-7A)
— southwest Dioxin
corner (EPA TO-
9A (mod))
Station #3: and PAH
East end of (EPA TO-
Park Place 13A)
Sidewalk
Bridge
Station #4:
East end of
Barclay St.
Sidewalk
Bridge
8
NYC-WTC 000096683
OCR can misread numbers and units. Confirm readings against the page image before using them.
NYC-WTC_000096683Source: NYC Law Department, mirrored locally
EPA Region 2 letter regarding revised environmental work plan submission for two buildings including asbestos, health, and safety assessment components.
EPA Region 2 letter regarding revised environmental work plan submission for two buildings including asbestos, health, and safety assessment components.