utilized during the shredding and bagging/containerization of the shredded waste
stream. In addition, no ACMremoved shall be shredded
o
6.3.4 Work Areas
This section indicates that the entire structure will be one work area. This approach
may
be problematic, as the entire work area will be abated, then cleaned then
cleared One floor couldn 't be under removal, while another floor was in the
cleaning stage or clearance stage, unless work area segregation occurs per floor or
group offloors. The single work area approach should be revisited before the work
plan isfinalized
0 6.3.5 Removals
This section includes procedures not in compliance with the current ,ICR 56. As
previously indicated, ifprocedures must be specified that aren't consistent with ICR
56 requirements, a site-specific variance must be obtained by the project designer as
an agentfor the owner, and the procedures and conditions contained within the sire-
specific variance decision must be incorporated into the work plan specified
asbestos project procedures.
• 6.4 OPERATION IV — IN PLACE ACM
No information is apparent within this section regarding the ACllrl window caulking at the
elevator mechanical room roofs, or the ACM window frame caulking at the first floor
exterior of the building. These materials were identified within Report Attachment IV, Table
I "Summary of Inspection Resultsfor Asbestos ". In addition, ACMfloor covering materials
are includea but nothing is included regarding the floor covering adhesives/mastics. These
materials should also be assumed and treated as ACM, unless appropriate bulk sampling
and analyses adequately show the materials to be nonACM.
Regardless of the listed ACMs, as previously indicated if procedures must be specified that
aren't consistent with ICR 56 requirements, a site-speck variance must be obtained by the
project designer the and the procedures and conditions contained
as an
agent for
owner,
within the site-speck variance decision must be incorporated into the work plan specified
asbestos project procedures.
7.3
SCAFFOLDING
A "Deconstruction and Scaffold Layout Plan" was referenced within this section, but not
apparent within the documents". The document detailing all appropriate procedures for
this
work
must
be
included
with the
workplan.
Phone;
(518)
457-1536
Fax:
(518)
457-1301
Averell
W,
State
Harriman
Office
Campus, Blda_
12,
Room
154. Albanv. NY 1994n
wwwia bo r.
state. ny.
us
NYC-WTC 000095865
OCR can misread numbers and units. Confirm readings against the page image before using them.