7.5 DEMOLITION SEQUENCE
No information was apparent in this section regarding sequencing of removals, cleaning
and clearance at the contaminated elevator shafts or other remaining contaminated utility
areas, prior to commencement of the general deconstruction of the building.
7.6 WASTE MANAGEMENT — CONVENTIONAL DEMOLITION
The only information regarding exterior ACM removals included a generalized statement
that the nonfriable asbestos spandrel flashing would be removed during "conventional
demolition". No information was apparent in this section regarding specific asbestos
project details for all the exterior ACM removals, which must be completed prior to
commencement of the general deconstruction of the building.
The Department anticipates that these issues will be appropriately addressed within revised versions
of these documents. If you have any questions regarding these comments please contact our office
at (518) 457-1536.
Sincerely,
4
Christopher G. Alonge, P.E.
Senior Safety and Health Engineer
ec Krish Radhakrisbnan, P.E. - NYC DEP
Gil Gillen — USDOL/OSHA
Robert Iulo — NYC DOB
Richard Frarn — NYS DEC
Norma Aird — NYS DOL
05-0919
Phone: (518) 457-1536 Fax: (518) 467-1301
W. Avereli Harriman State Office Campus, Bldg. 12, Room 154, Albany, NY 12240
www. la bo r.state.ny. us
NYC-WTC 000095866
OCR can misread numbers and units. Confirm readings against the page image before using them.