Folder label / City-provided: 114 LIBERTY 1 OF 2

18 documents · 45 pages

Silica test results for 114 Liberty Street, April 2003 ↗

NYC-WTC_000155054 – NYC-WTC_000155057

Submission of silica testing results and final report delivery schedule for the 114 Liberty Street project.

4 pages
Dioxin results review status memo, 114 Liberty Street, April 2003 ↗

NYC-WTC_000155093

Memo confirming EPA receipt of dioxin testing results and reporting methods for the building cleanup project.

1 pages
Dioxin results review status memo, 114 Liberty Street, April 2003 ↗

NYC-WTC_000155094 – NYC-WTC_000155095

Memo confirming EPA received dioxin test results and is currently reviewing the reporting methodology.

2 pages
DEP contract completion wrap-up memo, 114 Liberty Street, April 2003 ↗

NYC-WTC_000155096 – NYC-WTC_000155097

Memo documenting the completion of all DEP contracts and the final closure date for the interior cleanup program.

2 pages
DEP cleanup completion confirmation memo, 114 Liberty Street, April 2003 ↗

NYC-WTC_000155098 – NYC-WTC_000155099

Memo specifying that the final contract work and ledge clean-up were completed in late March 2003.

2 pages
Asbestos test results for 114 Liberty Street, April 2003 ↗

NYC-WTC_000155103 – NYC-WTC_000155108

Notification of failing asbestos results and request to increase crew size for re-cleaning at 114 Liberty Street.

6 pages
DEP interior cleaning background memo, 114 Liberty Street, February 2003 ↗

NYC-WTC_000155109 – NYC-WTC_000155110

Letter providing background on the proposed DEP cleaning of the damaged residential building located across from the WTC site.

2 pages
DEP interior cleaning proposal memo, 114 Liberty Street, February 2003 ↗

NYC-WTC_000155111 – NYC-WTC_000155117

Memo providing background on the building's structural damage and proposing a DEP-led interior cleaning program.

7 pages
FEMA and DEP coordination meeting memo, 114 Liberty Street, February ↗

NYC-WTC_000155118 – NYC-WTC_000155121

Correspondence regarding a joint meeting with building owners to discuss cleanup timelines, funding options, and EPA clearance requirements.

4 pages
EPA-DEP coordination memo on mold inspection and building cleanup, July ↗

NYC-WTC_000155136 – NYC-WTC_000155137

EPA correspondence to DEP regarding scope of work language for mold inspections and requesting a list of unoccupied, uncleaned buildings with cleanup status for congressional…

2 pages
Site visit report clarification memo, 114 Liberty Street, December 2002 ↗

NYC-WTC_000155145 – NYC-WTC_000155146

Response to a resident clarifying details from a site visit report regarding apartment layout and commercial unit locations.

2 pages
Letter to FEMA regarding 114 Liberty Street WTC damage, Feb ↗

NYC-WTC_000155160 – NYC-WTC_000155161

Formal letter correcting FEMA facts about debris collision and toxic dust exposure at the building.

2 pages
DEP internal memo assigning project managers for cleanup contracts, Feb ↗

NYC-WTC_000155162

Memo designating staff as project managers for cleanup and air monitoring contracts at 114 and 125 Liberty Street.

1 pages
DEP internal memo assigning project managers for cleanup contracts, Feb ↗

NYC-WTC_000155167

Memo designating staff as project managers for cleanup and air monitoring contracts at 114 and 125 Liberty Street.

1 pages
DEP memo re: Schedule A requirements, 114 Liberty, February 2003 ↗

NYC-WTC_000155173

DEP correspondence addressing contract Schedule A requirements and liability insurance requirements for 114 Liberty cleaning and monitoring work.

1 pages
DEP memo re: building access, 114 Liberty, Feb 2003 ↗

NYC-WTC_000155187 – NYC-WTC_000155190

Memo regarding building and unit access requests for 114 Liberty.

4 pages
Cleanup delay notice, 114 Liberty, March 2003 ↗

NYC-WTC_000155230

Notification of work delay due to snow and building activity at 114 Liberty.

1 pages
Rodent incident notice, 114 Liberty, March 2003 ↗

NYC-WTC_000155245

Memo alerting staff to a rat bite incident in the building and requesting precautions.

1 pages