DEP Hard Copies (68 Boxes) / DEP Box 31 / INDEPENDENCE PLAZA
NYC-WTC_000154938Machine-extracted title Lab reportSummary Hudson River Management LLC requests asbestos testing of carpeting at Independence Plaza before removal.
Subsequent re-testing and TEM analysis conducted on 10.24.01 revealed
that there was no airborne asbestos in the corridor.
DEP Hard Copies (68 Boxes) / DEP Box 31 / 114 LIBERTY 1 OF 2
NYC-WTC_000155034Machine-extracted title Permit applicationSummary Facsimile transmission of a permit application for 114 Liberty Street involving FEMA recovery efforts.
ASBESTOS ABATEMENT CONTRACTOR
12. Name Contracting, Inc. 13. Contact Person Mr. Robert Middleton
14.
DEP Hard Copies (68 Boxes) / DEP Box 31 / Buildings 105 Duane 80 John Gateway etc. 75 Park 200 Rector Trinity Church
NYC-WTC_000154677Machine-extracted title Permit applicationSummary Application form for notifying the Department of Buildings and Environmental Protection regarding an asbestos inspection project.
ASBESTOS ABATEMENT CONTRACTOR
.. PAL Environmental Safety Corp. 13.
DEP Hard Copies (68 Boxes) / DEP Box 31 / Buildings 105 Duane 80 John Gateway etc. 75 Park 200 Rector Trinity Church
NYC-WTC_000154680Machine-extracted title Permit applicationSummary Application form submitted to the Department of Environmental Protection for notification of an asbestos inspection project.
NYC 9/11 Public Portal Document
FAL PROTECTION
- Asbestos
DEP Hard Copies (68 Boxes) / DEP Box 31 / 114 LIBERTY 1 OF 2
NYC-WTC_000154966Machine-extracted title Permit applicationSummary Official DEP form notifying authorities of planned asbestos abatement activities at 114 Liberty Street.
Total amount of asbestos-containing material to be abated during this work
0®®.
DEP Hard Copies (68 Boxes) / DEP Box 31 / Buildings 105 Duane 80 John Gateway etc. 75 Park 200 Rector Trinity Church
NYC-WTC_000154675Machine-extracted title Permit applicationSummary Application form for notifying the Department of Buildings and Environmental Protection regarding an asbestos inspection project.
d) mt ASBESTOS PROJECT NOTIFICATION I
(ASBESTOS INSPECTION
DEP Hard Copies (68 Boxes) / DEP Box 31 / Buildings 105 Duane 80 John Gateway etc. 75 Park 200 Rector Trinity Church
NYC-WTC_000154594Machine-extracted title Lab reportSummary Letter from a complainant regarding improper asbestos cleanup at 333 [name] and requesting reinvestigation of test results.
Enclosed is a copy of the complaint with the test results indicating the presence of
asbestos a 333 Rector Place in excess of 1%.
DEP Hard Copies (68 Boxes) / DEP Box 31 / 114 LIBERTY 1 OF 2
NYC-WTC_000154955Machine-extracted title Lab reportSummary Federal agencies respond to resident concerns regarding the validity of environmental clearance data for 114 Liberty Street.
Therefore, this space within the building is not considered to have met the
primary clearance value for asbestos.
DEP Hard Copies (68 Boxes) / DEP Box 31 / 114 LIBERTY 2 OF 2
NYC-WTC_000155263Machine-extracted title Permit applicationSummary Notice instructing that original WTC documents must be preserved as evidence and not disposed of.
Therefore, this space within the building is not considered to have met the
primary clearance value for asbestos.
DEP Hard Copies (68 Boxes) / DEP Box 31 / 114 LIBERTY 1 OF 2
NYC-WTC_000154940Machine-extracted title Lab reportSummary EPA confirms that primary and secondary clearance levels for contaminants at 114 Liberty Street have been met.
Your staff has identified the area of the building
that contains the pizza shop as having asbestos-containing material (ACM).
DEP Hard Copies (68 Boxes) / DEP Box 31 / 114 LIBERTY 1 OF 2
NYC-WTC_000154998Machine-extracted title Lab reportSummary EPA confirms that primary and secondary clearance levels for contaminants at 114 Liberty Street have been met.
Therefore, this space within the building is not considered to have met the
primary clearance value for asbestos.
DEP Hard Copies (68 Boxes) / DEP Box 31 / 114 LIBERTY 1 OF 2
NYC-WTC_000155009Machine-extracted title Lab reportSummary Federal agencies respond to resident concerns regarding the validity of environmental clearance data for 114 Liberty Street.
Your staff has identified the area of the building
that contains the pizza shop as having asbestos-containing material (ACM).
DEP Hard Copies (68 Boxes) / DEP Box 31 / Buildings 105 Duane 80 John Gateway etc. 75 Park 200 Rector Trinity Church
NYC-WTC_000154697Machine-extracted title Permit applicationSummary Application form submitted to the Department of Environmental Protection for notification of an asbestos inspection project.
ASBESTOS ABATEMENT CONTRACTOR
12. Name __13. Conta si Person
14.
DEP Hard Copies (68 Boxes) / DEP Box 31 / Buildings 105 Duane 80 John Gateway etc. 75 Park 200 Rector Trinity Church
NYC-WTC_000154698Machine-extracted title Permit applicationSummary Application form submitted to the Department of Environmental Protection for notification of an asbestos inspection project.
ASBESTOS ABATEMENT CONTRACTOR
12. Name 13. Contact Person
14.
DEP Hard Copies (68 Boxes) / DEP Box 31 / 114 LIBERTY 1 OF 2
NYC-WTC_000154953Machine-extracted title Lab reportSummary Federal agencies respond to resident concerns regarding the validity of environmental clearance data for 114 Liberty Street.
The Department did not perform a complete survey or hazard
assessment for asbestos.
DEP Hard Copies (68 Boxes) / DEP Box 31 / 114 LIBERTY 1 OF 2
NYC-WTC_000155007Machine-extracted title Lab reportSummary Federal agencies respond to resident concerns regarding the validity of environmental clearance data for 114 Liberty Street.
The Department did not perform a complete survey or hazard
assessment for asbestos.
DEP Hard Copies (68 Boxes) / DEP Box 31 / INDEPENDENCE PLAZA
NYC-WTC_000154937Machine-extracted title Lab reportSummary Hudson River Management LLC requests asbestos testing of carpeting at Independence Plaza before removal.
be removed and disposed of in accordance with all laws governing asbestos
abatement.
DEP Hard Copies (68 Boxes) / DEP Box 31 / DEUTSCHE BANK
NYC-WTC_000154845Machine-extracted title Memo or letterSummary Internal routing form regarding handling of Deutsche Bank documents related to World Trade Center legal proceedings.
Exhibit B contains the analysis results for asbestos, mercury and other heavy metals. The results indicate
that asbestos is present throughout the building in amounts exceeding one per cent.
DEP Hard Copies (68 Boxes) / DEP Box 31 / Buildings 105 Duane 80 John Gateway etc. 75 Park 200 Rector Trinity Church
NYC-WTC_000154642Machine-extracted title Memo or letterSummary Letter from DEP responding to concerns about asbestos in the building at 105 [name] following the World Trade Center collapse.
The
Bureau of results were that no asbestos structures were detected.
DEP Hard Copies (68 Boxes) / DEP Box 31 / 125 CEDAR 1 OF 2
NYC-WTC_000155902Machine-extracted title FormSummary Cover sheet for a confidential fax from legal counsel to the EPA regarding comments on the 125 Cedar Street project.
We have been advised that the cleaning will be
done by certified asbestos remediation contractors. Is that