Change order submission memo, Dec 1999 — page 1
Summary Letter submitting change order #108 for fiber optic video cable connections and test splices at the Mayor's Office of Emergency Management.
No matching passage to preview on this page.
Email alerts are not offered yet — copy this link to check back after a new release.
Browsing all mirrored pages. Enter a keyword, address or Bates number to narrow this.
Summary Letter submitting change order #108 for fiber optic video cable connections and test splices at the Mayor's Office of Emergency Management.
No matching passage to preview on this page.
Summary Change order for painting smoke room at Mayor's Office of Emergency Management facility, $650.
No matching passage to preview on this page.
No matching passage to preview on this page.
No matching passage to preview on this page.
Summary Letter submitting change order #104 for galvanized riser and fiber optic cable installation for telephone and camera systems at 7 World Trade Center.
No matching passage to preview on this page.
Summary Letter submitting change order #103 for audiovisual press feed and camera system work on the 1st, 7th, and 23rd floors at 7 World Trade Center.
No matching passage to preview on this page.
Summary Letter submitting change order #102 for electrical modifications on the 1st, 7th, and 23rd floors at the Mayor's Office of Emergency Management.
No matching passage to preview on this page.
Summary Letter submitting change order #101 for a wall-mounted Halotron 1 fire extinguisher at the Mayor's Office of Emergency Management facility.
No matching passage to preview on this page.
Summary Change order for engineering work related to facility systems and infrastructure, $20,625.
No matching passage to preview on this page.
Summary Contractor submission for Change Order #99 to install separate electrical circuits in executive and coffee areas.
No matching passage to preview on this page.
Summary Contractor submission for $9,092 to convert press room lights to hard-wired switch legs and eliminate plug-in feeds.
No matching passage to preview on this page.
Summary Memo approving an invoice for construction rent payments at 7 World Trade Center and requesting processing of the $1,884,322.00 payment.
No matching passage to preview on this page.
Summary Letter submitting change order #97 for enclosing fuel oil lines with sheetrock assembly at the Mayor's Office of Emergency Management.
No matching passage to preview on this page.
Summary Change order #096 for $10,225 to furnish and install heat tracing on hot water line at 7 World Trade Center Mayor's Office, 1st, 7th, and 23rd floors.
No matching passage to preview on this page.
Summary Letter submitting change order #95 to install three new electrical receptacles under a conference room table for $1,046.
No matching passage to preview on this page.
Summary Change order #094 (revised) for $10,417 to furnish and install automatic air release valve and visual level indicator at 7 World Trade Center.
No matching passage to preview on this page.
Summary Letter submitting change order #94 to install equipment following a domestic transfer pump test for $7,291.
No matching passage to preview on this page.
Summary Letter submitting change order #093 to wire shade motors and controllers with new circuits for $4,892.
No matching passage to preview on this page.
Summary Letter submitting Change Order #92 for installing a wall-mounted kindoff in the press room.
No matching passage to preview on this page.
Summary Letter submitting change order #91 for $6,565 to remedy water leakage on the 7th floor of 7 World Trade Center.
No matching passage to preview on this page.