Specifications for asbestos-containing exterior sealants and caulking materials abatement.

NYC-WTC_000454574–000454656
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

SECTION 02082

5. Dumping of debris, waste or bagged waste will not be permitted.

6. Cleanup of visible accumulations of loose ACM shall occur whenever there is a sufficient amount to fill a single asbestos bag.

7. ACM shall be collected utilizing rubber dust pans and rubber squeegees.

8. HEPA vacuums shall not be used on wet materials unless specifically designed for that purpose.

9. Metal shovels shall not be used within the work area.

10. Accumulations of dust shall be cleaned off all surfaces of the Work Area daily.

11. Mastic solvent when used will be applied in moderation (e.g. by airless sprayer). Saturation of the concrete floor with mastic solvent must be avoided.

12. The Contractor shall retain all items in the storage area in an orderly arrangement allowing maximum access, not impeding traffic, and providing the required protection of all materials.

13. The Contractor shall not allow accumulation of scrap, debris, waste material, and other items not required for use in this work, When asbestos contaminated waste must be kept on the work site overnight or longer, it shall be double bagged and stored in tightly closed and sealed fiber drums, placed inside or outside the contaminated area.

14. At least twice a week (more if necessary), the Contractor shall completely remove all scrap, debris and waste material from the job site.

15. The Contractor shall provide adequate storage space for all items awaiting removal from the job site, observing all requirements for fire protection and concerns for the environment.

16. All respiratory protection equipment shall be selected from the latest NIOSH Certified Equipment list.

17. Daily and more often, if necessary, the Contractor shall inspect the Work Areas and adjoining spaces, and pick u all scrap, debris, and waste material. Al such items shall be removed to the place designated for their storage.

18. Weekly, and more often, if necessary, the Contractor shall inspect all arrangements of materials stored on the site; re-stack and tidy them or otherwise service them to meet the requirements of these Specifications.

19. The Contractor shall maintain the site in a neat and orderly condition at all times.

02082-60

CITY_21 MCI 00_014563833

NYC-WTC_000454633

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000454633Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →