Mr. Bernard P. Orlan
January 31,2002
Page 2
• At the request of UFT and PTA representatives, aggressive air clearance sampling shall
be performed throughout the entire building following the successful visual inspection
following the cleaning. Air sampling shall be conducted in compliance with all
applicable local, state and federal regulations.
• Air samples shall be analyzed via Transmission Electron Microscopy (TEM)
methodology. Successful air clearance shall be achieved when all air samples collected
within the building are below 70 structures per millimeter squared (<70 str/mm^) - TEM
analysis.
• Prior to commencement of the project, the Contractor shall submit the following items to
NYC BOE for approval:
1. A written Project Approach detailing how the said work shall be performed.
2. An estimated cost for the work.
3. A Project Schedule listing manpower, shift durations, phases and start and
completion dates.
If you have any questions or comments regarding the scope of work, please do not hesitate to
contact us at your earliest convenience.
Sincerely,
ATC ASSOCIATES INC.
Mark^erjesen
Senior Project Manager
MT/dc