GRACE CONTRACTING CORP. 151.45 6th Road, Whitestone, N.Y. 11357-(718) 767-9000 DATE: 1/23/02 DAY FINAL
DAILY WORK FORCE REPORT
Job Name & Location: World Trade Center Contract No. Weather Conditions
Labor I Equipment CLASSIFICATION QUANT. Il Description MANNED STANDBY IDLE SUPERINTENDENT 2 '|CAT 966 LOADER 1 PROJECT ENGINEER 2 ' CAT 973 LOADER ~ 1 OFFICE ENGINEER ' CAT 365 GRAPPLER ~ 1 FOREMEN 1 ' CAT 375 GRAPPLER ~ 1 SAFETY OFFICER 1 ' |CAT 375 GRAPPLER 1 LABORERS 8 ' HITACHI 750 GRAPPLER 1 IRON WORKERS ■ HITACHI 550 GRAPPLER LOCAL 14 5 ' HITACHI 1200 GRAPPLER 1 LOCAL 15 4 ■ 185 CFM COMPRESSOR 1 CARPENTER ■ 235 HAMMER HOE RAM CARPENTER FOREMAN 1 ■ MECHANICS TRUCK 2 TEAMSTERS (FUEL) 1 ■ TOOL TRUCK MECHANICS 2 'TOOL VAN 1 HOUSE WRECKERS 1 ■ ROLL OFF ■ DUMP TRAILERS 8 ■ LOW BED TRAILER 2 ■ HIGH DECK TRAILERS ■ WELDING TRUCK 1 DELIVERIES: AWISCO 4 TICKETS ■ FUEL TRUCK 1 ■ PICKUP TRUCKS 8 ■ LIGHT TOWERS 5 ■ SITE MULE 3 •NOTE: WTC TRUCKING 14 DRIVERS ■ DUMP TRUCKS ■ 10 WHEEL DUMP TRUCK ■ FLASHING ARROW BOARD ' OFFICE TRAILER/GENER. 1 ■ CARGO BOXES 4 ' FLAT TRUCK 1 PUMP 2 LIGHT TOWERS USED 2.5 HOURS
Description of Work:
CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF TOWER TWO TO ACCOMMODATE BRIDGE MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA___________________________________________ LOADS OUT 87________________________________________________________________________ YUKELOADS 157_______________ DOT LOADS OUT 115____________________________________________________________________ DELAYS:
GRACE CONTRACTING CORP Approved By: BY: Title: For: SUPERINTENDENT
DAILY WORK FORCE REPORT0123D.xls 02.214764
CITY_21MC100_001046859 NYC-WTC_000429403
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000342309
Day final workforce and equipment for World Trade site, Jan 23, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.996
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000263633
Day shift daily workforce and equipment at World Trade site, Jan 23, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.995
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305461
Night preliminary daily crew and equipment listing for World Trade Center site, Jan 23, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.994
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305462
Day final daily crew and equipment listing for World Trade Center site, Jan 23, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.994
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429401
Day shift daily workforce and equipment details for World Trade site on 1/22/02.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000263632
Night shift daily workforce and equipment at World Trade site, Jan 22, 2002.
2 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305346
Daily workforce and equipment listing for World Trade Center project site, including labor and machine counts.
2 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000291404
Day final daily workforce report for World Trade site, Dec 15, 2001.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000280105
Day final daily workforce and equipment for World Trade Center, Dec 15, 2001.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000263635
Day shift daily workforce and equipment at World Trade site, Jan 24, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000342311
Day final workforce and equipment listing for World Trade, Jan 24, 2002.
2 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000388390
Day shift final daily workforce at World Trade Center, Dec 17, 2001.
1 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Page similarity is temporarily unavailable or this page has no indexed vector.
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000342309
Day final workforce and equipment for World Trade site, Jan 23, 2002.
Similar indexed content
NYC-WTC_000263633
Day shift daily workforce and equipment at World Trade site, Jan 23, 2002.
Similar indexed content
NYC-WTC_000305461
Night preliminary daily crew and equipment listing for World Trade Center site, Jan 23, 2002.
Similar indexed content
NYC-WTC_000305462
Day final daily crew and equipment listing for World Trade Center site, Jan 23, 2002.
Similar indexed content
NYC-WTC_000429401
Day shift daily workforce and equipment details for World Trade site on 1/22/02.
Similar indexed content