Ambient Air Monitoring Program Section No. 6
Quality Assurance Project Plan Revision No.: 0
130 Liberty Street - NY, NY Date: August 2005
Lower Manhattan Development Corporation Page 19 of 116
The Initial Building Characterization Study that was released in September identified the need
for supplemental testing to be performed in areas that were previously inaccessible prior to
LMDC taking ownership of the building. Once LMDC acquired the building in August, 2004 the
supplemental testing occurred in the building’s vertical shafts, interior wall interstitial spaces,
HVAC system, cell system, curtain wall cavity, and the exterior. These test results were released
in January, 2005 and will be used as a basis for amending the deconstruction plan.
Cleaning and Deconstruction Work
In December, 2004 the LMDC released the draft Phase I Deconstruction Plan and formally
submitted the plan to Federal, State and City Regulatory Agencies for review and comment. The
proposed Deconstruction Plan submitted for review to the government regulators provided that
the 130 Liberty Street building will be deconstructed in three phases:
• Phase I - Preparation Phase
• Phase I - Asbestos and COPC Abatement and Removal
• Phase II - Structural Deconstruction
The Phase I - Preparation Phase includes the erection of scaffolding and hoists on the full extent
of the exterior of the building, construction of interior hoist vestibules, erection of sidewalk
sheds and perimeter fencing, exterior negative pressure tent enclosures to implement the Pilot
Program, localized roof, facade and general exterior area clean-up and the removal of existing
netting on the exterior of the building.
Phase I Asbestos and COPC Abatement and Removal Phase includes the cleaning and removal
of all interior surfaces and non-structural elements within the building under containment. The
clean-up and abatement will be conducted so that the building at 130 Liberty (Building) can be
safely deconstructed to allow for redevelopment of the WTC Site. Phase I of the Deconstruction
Project will occur while the work area is placed under negative pressure containment and
includes the following general categories: (a) the general area cleanup of WTC dust and debris,
(b) removal and disposal of installed porous and certain non-porous building materials and
components, (c) cleaning and salvage of certain installed non-porous building equipment and
components, (d) removal of building materials containing asbestos which were present in the
Building prior to September 11*, 2001 (referred to herein as “ACBM”), primarily within the
Building interior, (e) packaging of asbestos and other regulated waste including, but not limited
to light bulbs, lighting ballasts, batteries, mercury-containing thermostats, etc. at generation
points, movement of containers to the decontamination unit and movement of decontaminated
containers to waste loading using an exterior hoist or crane, and (f) cleaning of exterior surfaces
of the Building (i.e. building washdown).
During all Phase I activities, a minimum buffer zone of three floors initially for the top three
floors and then two floors thereafter, will be maintained between the active abatement and
cleanup (Phase 1) area and the exterior abatement/structural demolition (Phase 11) portion of the
project. The proposed cleanup and abatement will be conducted so that the Building can be
L2005-346 Rev. 1
CITY_DEP_WORBY_CANNATA_SUBP_000114660